Prior to the enactment of AB 1888, the term "Focused EIR" was neither defined in CEQA nor in the CEQA Guidelines. Nonetheless, it has been commonly used to describe subsequent EIRs, or EIRs prepared subsequent to a program EIR where analysis was narrowed to those effects resulting from the subsequent project. Now, Section 21158 explicitly defines a Focused EIR as "an environmental impact report on a subsequent project identified in a master environmental impact report." Although program EIRs and other procedures for focusing EIRs (and environmental analysis) continue in full force, their product may no longer properly be termed a "Focused EIR."
A Focused EIR is used when, after preparation of an initial study for a subsequent project under the Master EIR, the Lead Agency specifically finds that the Master EIR's analyses of cumulative impacts, growth inducing impacts, and irreversible significant effects are adequate for the subsequent project. The finding and supporting evidence should be included in the Focused EIR (see Appendix 1). Absent this finding, a standard EIR would be required.
A Focused EIR must incorporate by reference the Master EIR. Pursuant to CEQA Guidelines Section 15178(c), the analysis contained in a Focused EIR is limited to the following:
A Focused EIR need not examine those significant environmental effects which the lead agency, prior to releasing the draft Focused EIR for review, finds, on the basis of the initial study, related documents, and commitments from the project proponent, were either:
The draft Focused EIR must include these relevant findings of exception when it is released for review.
Note that effects for which MEIR findings were previously made pursuant to CEQA Guidelines Section 15091(a)(3) are not included in the above exception. Findings under paragraph (3) relate to those significant effects identified in the Master EIR for which mitigation measures or alternatives were found to be infeasible due to specific economic, social, or other considerations. The conspicuous absence of any reference to paragraph (3) seems to indicate that these significant unavoidable effects must be addressed in the Focused EIR. OPR recommends that unmitigated effects be examined in the context of the limitations on analysis described above.
Section 21158.5 and CEQA Guidelines Section 15179.5 authorizes a streamlined review process for selected projects through use of Focused EIRs. Where a project consists of a multi-family residential development of not more than 100 dwelling units, or a residential and commercial or retail mixed-use development of not more than 100,000 square feet in area which complies with all the following, a Focused EIR shall be prepared, notwithstanding that the project was not identified in a Master EIR. In order to qualify to use this provision, a Lead Agency must make the following findings regarding the project:
The scope of a Focused EIR prepared under Section 21158.5 is limited to the following:
Although the above bears passing resemblance to the seldom-used process
for streamlining review of later projects under a general plan, specific
plan, or zoning EIR pursuant to Section 21083.3, the two operate independently.
Section 21083.3 provides that the application of CEQA to any project that
is consistent with zoning, a community plan, or general plan for which an
EIR was certified is limited to "those effects on the environment which
are peculiar to the parcel or to the project and which were not addressed
as significant effects in the prior environmental impact report, or which
substantial new information shows will be more significant than described
in the prior environmental impact report." Application of Section 21158.5
and Guidelines Section 15179.5 are qualified as noted above.