Governor's Office of Planning and Research
The California Environmental Quality Act (CEQA) was enacted in 1970 as a system of checks and balances for land-use development and management decisions in California.
Environmental review is characterized by an Environmental Impact Report (EIR). The EIR records the scope of the applicant's proposal and analyzes all its known environmental effects. Project information is used by state and local permitting agencies in their evaluation of the proposed project
In 1977, the California Legislature passed the California Permit Streamlining Act (PSA) and established the Office of Permit Assistance (OPA). The creation of both OPA and PSA sought to remedy a complicated and often unresponsive permitting processes. The Permit Streamlining Act addressed some of CEQA's shortcomings: namely, that it lacked a calendar by which applicants and the public could expect the prompt review of a given project. The PSA added time-lines and deadlines to expedite government review of proposals. While this did not guarantee the approval of projects or their favorable review, it did give applicants and the public an orderly, standardized process for filing reports and actions.
California's environmental review is rigorous by anyone's standards. In most cases it extends beyond federal statutes established under the National Environmental Policy Act (NEPA).
In California, the development permit process is coordinated with the environmental review process under CEQA. Every development project which is not exempt from CEQA must be analyzed by the lead agency to determine the potential environmental effects of the project. This analysis is required by state law. It must be completed within specified time periods which are concurrent with the time periods in which an agency is required to approve or deny the project.
Once the lead agency is identified, all other involved agencies, whether
state or local, become responsible or trustee agencies. Responsible and
trustee agencies must consider the environmental document
prepared by the lead agency and do not, except in rare instances,
prepare their own environmental documents. The procedure for issuing each
particular development permit is governed by the particular law which establishes
the permit authority and by the California Permit Streamlining Act.
There are three major phases in the development process as provided by CEQA and the PSA:
I. Pre-Application Phase:
The Pre-Application Phase begins when the developerapplicant has completed the conceptual and preliminary design work for a project and is ready to prepare a project proposal. At this point, enough information should be available to describe project activities and to identify the project's proposed location. The primary objective of this phase is to identify the appropriate permitting agencies and to collect as much relevant background information possible.
Many proposals (projects) will require special studies either before or during the formal processing of the application. All state and local agencies are required to list the type of information and the criteria they will use in evaluating a project application. DeveloperApplicants may request preapplication conferences or "scoping" meetings with the permitting agencies to discuss how agencies' specific rules will apply to their proposed projects.
By the end of the preapplication phase, the developer-applicant should have a good understanding of the detailed project information required, a list of probable permitting agencies, and an indication of the degree of environmental analysis required by the agencies.
At this point, the applicant will learn which agency (if there will be
more than one permitting agency) will be the "lead agency." The
lead agency is the single agency responsible for determining the type of
environmental analysis CEQA requires. In addition, the lead agency must
prepare the environmental review document it calls for. The agency with
the greatest authority over the project will usually assume the lead agency
role. Criteria for determining the lead agency are provided in the CEQA
Guidelines at Section 15051. In the event of a dispute over the lead agency
status between or among agencies, the Office of Planning and Research may
designate the lead. However, once the lead agency is identified, all other
involved agencies, whether state or local, become responsible or trustee
agencies.
II. The Application Phase:
The Application Phase begins with the filing of the necessary permit application forms along with a detailed project description. Supporting documents must also be filed, where CEQA requires, with the respective agencies. Unless otherwise specified, the sequence of filing applications is left up to the applicant. It must be noted, however, that the failure of some agencies to accept an application until certain other permit approvals have been granted does not in any way impact the time limits under which the agency must act.
During this phase, each receiving agency must review the submitted application to determine if the individual filing is complete. The lead agency must make its determination in writing within 30 days. Should the agency fail to make its determination within 30 days, the application will be deemed accepted as complete by operation of law. If the application is determined to be incomplete, the agency must specify the deficiencies and the manner in which the deficiencies may be corrected. The developerapplicant may then refile the corrected application. Upon refiling, the agency has another 30 days to review for completeness. If the application is again determined to be incomplete, the agency must provide a process for an appeal of the determination and reach a decision within 60 days. Further dispute may be adjudicated. This step is critical to the process. A permit may not be denied for failure to provide information not requested.
Once an application is accepted as complete, the lead agency has six
months to approve or disapprove a project for which an Environmental Impact
Report (EIR) has been certified. The time limit in all other cases is three
months after a negative declaration is adopted or an exemption issued.
III. Review Phase:
The Review Process begins immediately with the completion of the specific application. In recognition of §65941 of Chapter 4.5 of the Permit Streamlining Act, the lead agency will simultaneously review the project under the applicable permit rules and conduct the necessary environmental analysis. Permit rules vary depending on the particular permit authority in question, but the process generally involves comparing the proposed project with existing statutes. The procedure usually results in a public hearing followed by a written decision by the agency or its designated officer. Typically, a project may be approved, denied, or approved subject to specified conditions.
The CEQA procedure involves a number of steps which produce an environmental document examining the lead agency's as well as the responsible and/or trustee agencies' permit decisions.
The first step in the CEQA process is to determine whether the proposed project is subject to CEQA. There are a number of statutory and categorical exemptions. If the proposal is not covered by CEQA, the lead agency may file a Notice of Exemption. If the project is covered by CEQA, the lead agency must prepare an Initial Study to determine whether the project may have a significant adverse impact on the environment. The initial study must be completed within 30 days after an application is accepted as complete.
If the Initial Study shows that the project will not have a significant effect on the environment, the lead agency must prepare and circulate a Negative Declaration. Where potential significant effects are shown, but the project is modified such that the effects are rendered insignificant, the lead agency must prepare and circulate a mitigated Negative Declaration. In either case, the Negative Declaration must be circulated for review for 30 days and must be ready for adoption by the lead agency within 105 days after a completed application is accepted.
If, on the other hand, the Initial Study shows that the project may have one or more significant effects, the lead agency must circulate a Notice of Preparation (NOP) in anticipation of preparing an environmental impact report (EIR) and must consult with responsible and trustee agencies as to the content of the environmental analysis. Responsible agencies must respond to the NOP within 30 days. If a responsible or trustee agency fails to respond, the lead agency may assume that the responsible agency has no response to make. Further, if a responsible agency fails to respond or responds incompletely, the responsible agency may not subsequently raise issues or objections regarding the adequacy of the environmental review.
At the close of this period, the lead agency must prepare and circulate a Draft Environmental Impact Report (DEIR). All concerned agencies and the public may review the DEIR. All comments on the DEIR must be made within the 45 day review period.
At the close of the review and comment period, the lead agency must respond to the comments received. Comments from responsible or trustee agencies shall be limited to those project activities which are within the agency's area of expertise, are required to be carried out or approved by the agency, or will be subject to the exercise of powers by the agency.
The lead agency prepares and certifies a Final Environmental Impact Report (FEIR). If the lead agency approves the project, it must find that each significant impact will be mitigated below the level of significance where feasible, and that overriding social or economic concerns merit the approval of the project in the face of unavoidable effects.
With the CEQA and permit review process completed, the lead agency must approve or deny the permit within 6 months of certifying the EIR or within 3 months of adopting the Negative Declaration and file a Notice of Determination (NOD). Responsible agencies must then act within six months after the lead agency's action or, if the developerapplicant has not already filed an application with a responsible agency, within six months from the time the application is filed (except as modified under Health and Safety Code §25199.6).
Environmental documents for projects involving one or more state agencies
or involving issues of areawide or statewide significance must be sent to
the State Clearinghouse for distribution to interested state agencies. The
State Clearinghouse will link the lead agency with the responsible state
agencies.
There are several key points that agencies, developer-applicants and the public must be aware of in order to avoid misunderstandings and delays:
The permit and environmental review processes are complicated. There are often several agencies and many persons involved. Hundreds of laws and rules may apply to a particular project. Agencies are constantly revising their procedures and changing personnel. The Legislature and the Governor created the Office of Permit Assistance (OPA) within the Trade and Commerce Agency to help project applicants, localities and the public to understand CEQA and the permitting process. The primary mission of the Office of Permit Assistance is to provide assistance and information to parties interested in the permit process.
The Office of Permit Assistance can be contacted by telephone at 916/322-4245 (ATSS 473-4245). Its FAX number is (916) 322-3524. The mailing address is 801 K Street, Suite 1700, Sacramento, CA 95814.