Appendix D:Time Periods for Review of Environmental Documents |
|
|
|
|
|
| Review of application for completeness | Lead Agency has 30 days to review an application for completeness. If no determination is made within this period, it will be deemed complete |
|
15101 |
| Lead Agency acceptance of an application as complete | Begins maximum one-year period to complete environmental review for certain projects |
|
PRC 21100.2, 21151.5 |
| Initial Study | Provides 30 days to determine whether an EIR or Neg Dec will be required |
|
|
| Notice of Preparation | Provides 30 days from reciept of NOP for agencies to respond to the lead agency |
|
|
| Convening of Scope and Content meetings | Requires a meeting requested by an agency or by the applicant to be convened within 30 days of the request |
|
|
| Public Review | When an environmental document is submitted to the Clearinghouse, the public review period shall be at least as long as the review set by the Clearinghouse |
ND: 20-30 days |
|
| Review by state agencies | Provides standard 45 days for EIRs and standard 30 days for NDs, through State Clearinghouse |
ND: 30 days |
|
| Completion of Negative Declaration | For a private project, the Neg Dec must be adopted within 180 days after the application is complete |
|
PRC 21100.2, 21151.5 |
| Completion and certification of EIR | For a private project, an EIR must be completed within one year -- May be extended once for up to 90 days |
|
|
| Notice of Determination -- filing | Provides that the notice shall be filed within 5 days |
|
15094 |
| Notice of Determination -- challenges | Filing starts a 30-day statute of limitations to court challenges to the approval of the project |
|
15094 15112 |
| Suspension of time limits | Unreasonable delay of document preparation caused by the applicant allows suspension of time periods in Guidelines, Sections 15107 and 15108 |
|
|
| Projects with federal involvement | Time limits may be waived or superseded by federal time requirements |
|