65920. Permit Streamlining Act
(a) This chapter shall be known and may be cited as the Permit Streamlining Act.
(b) Notwithstanding any other provision of law, the provisions of this chapter shall apply to all public agencies to the extent specified in this chapter, except that the time limits specified in Division 2 (commencing with Section 66410) of Title 7 shall not be extended by operation of this chapter.
(Amended by Stats. 1982, Ch. 87. Effective March 1, 1982; Amended by Stats. 1996, Ch. 799.)
65921. Policy
The Legislature finds and declares that there is a statewide need to ensure clear understanding of the specific requirements which must be met in connection with the approval of development projects and to expedite decisions on such projects. Consequently, the provisions of this chapter shall be applicable to all public agencies, including charter cities.
(Added by Stats. 1977, Ch. 1200.)
65922. Exemptions
The provisions of this chapter shall not apply to the following:
(a) Activities of the State Energy Resources Development and Conservation Commission established pursuant to Division 15 (commencing with Section 25000) of the Public Resources Code.
(b) Administrative appeals within a state or local agency or to a state or local agency.
(Amended by Stats. 1982, Ch. 87. Effective March 1, 1982.)
65922.1. Exception
During a year declared by the State Water Resources Control Board or the Department of Water Resources to be a critically dry year, or during a drought emergency declared by the Governor pursuant to Chapter 7 (commencing with Section 8550) of Division 1 of Title 2, the time limits established by this chapter shall not apply to applications to appropriate water pursuant to Part 2 (commencing with Section 1200) of Division 2 of, to petitions for change pursuant to Chapter 10 (commencing with Section 1700) of Part 2 of Division 2 of, or to petitions for certification pursuant to Section 13160 of, the Water Code for projects involving the diversion or use of water.
(Added by Stats. 1991, Ch. 12 of extraordinary session. Effective October 9, 1991.)
65922.3. to 65923.5. (Repealed by Stats. 1993, Ch. 56)
65923.8. Informing applicant of OPA existence
Any state agency which is the lead agency for a development project shall inform the applicant for a permit that the Office of Permit Assistance has been created in the Office of Planning and Research to assist, and provide information to, developers relating to the permit approval process.
(Added by Stats. 1983, Ch. 1263.)
65924. Deadlines
With respect to any development project an application for which has been accepted as complete prior to January 1, 1978, the deadlines specified in Sections 65950 and 65952 shall be measured from January 1, 1978. With respect to such application received prior to January 1, 1978, but not determined to be complete as of that date, a determination that the application is complete or incomplete shall be made not later than 60 days after the effective date of the act amending this section in 1978.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978.)
65925. Definitions
Unless the context otherwise requires, the definitions in this article govern the construction of this chapter.
(Added by Stats. 1977, Ch. 1200.)
65926. Air pollution control district
"Air pollution control district" means any district created or continued in existence pursuant to the provisions of Part 3 (commencing with Section 40000) of Division 26 of the Health and Safety Code.
(Added by Stats. 1977, Ch. 1200.)
65927. Development
"Development" means, on land, in or under water, the placement or erection of any solid material or structure; discharge or disposal of any dredged material or of any gaseous, liquid, solid, or thermal waste; grading, removing, dredging, mining, or extraction of any materials; change in the density or intensity of use of land, including, but not limited to, subdivision pursuant to the Subdivision Map Act (commencing with Section 66410 of the Government Code), and any other division of land except where the land division is brought about in connection with the purchase of such land by a public agency for public recreational use; change in the intensity of use of water, or of access thereto; construction, reconstruction, demolition, or alteration of the size of any structure, including any facility of any private, public, or municipal utility; and the removal or harvesting of major vegetation other than for agricultural purposes, kelp harvesting, and timber operations which are in accordance with a timber harvesting plan submitted pursuant to the provisions of the Z'berg-Nejedly Forest Practice Act of 1973 (commencing with Section 4511 of the Public Resources Code).
As used in this section, "structure" includes, but is not limited to, any building, road, pipe, flume, conduit, siphon, aqueduct, telephone line, and electrical power transmission and distribution line.
Nothing in this section shall be construed to subject the approval or disapproval of final subdivision maps to the provisions of this chapter.
"Development" does not mean a "change of organization", as defined in Section 56021, or a "reorganization", as defined in Section 56073.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978; Amended by Stats. 1986, Ch. 688; Amended by Stats. 1992, Ch. 1003.)
65928. Development project
"Development project" means any project undertaken for the purpose of development. "Development project" includes a project involving the issuance of a permit for construction or reconstruction but not a permit to operate. "Development project" does not include any ministerial projects proposed to be carried out or approved by public agencies.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978.)
65928.5. Geothermal field development
"Geothermal field development project" means a development project as defined in Section 65928 which is composed of geothermal wells, resource transportation lines, production equipment, roads, and other facilities which are necessary to supply geothermal energy to any particular heat utilization equipment for its productive life, all within an area delineated by the applicant.
(Added by Stats. 1978, Ch. 1271.)
65929. Lead agency
"Lead agency" means the public agency which has the principal responsibility for carrying out or approving a project.
(Added by Stats. 1977, Ch. 1200.)
65930. Local agency
"Local agency" means any public agency other than a state agency. For purposes of this chapter, a redevelopment agency is a local agency and is not a state agency.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978.)
65931. Project
"Project" means any activity involving the issuance to a person of a lease, permit, license, certificate, or other entitlement for use by one or more public agencies.
(Added by Stats. 1977, Ch. 1200.)
65932. Public agency
"Public agency" means any state agency, any county, city and county, city, regional agency, public district, redevelopment agency, or other political subdivision.
(Added by Stats. 1977, Ch. 1200.)
65933. Responsible agency
"Responsible agency" means a public agency, other than the lead agency, which has responsibility for carrying out or approving a project.
(Added by Stats. 1977, Ch. 1200.)
65934. State agency
"State agency" means any agency, board, or commission of state government. For all purposes of this chapter, the term "state agency" shall include an air pollution control district.
(Added by Stats. 1977, Ch. 1200.)
65940. List specifying required data for development project
Each state agency and each local agency shall compile one or more lists which shall specify in detail the information that will be required from any applicant for a development project. The list or lists may include the consolidated project information form developed pursuant to Section 65946. Each local agency shall revise the list of information required from an applicant to include a certification of compliance with Section 65962.5, and the statement of application required by Section 65943. Copies of the information, including the statement of application required by Section 65943, shall be made available to all applicants for development projects and to any person who requests the information.
(Amended by Stats. 1982, Ch. 84; Amended by Stats. 1986, Ch. 1048 and Ch. 1019; Amended by Stats. 1987, Ch. 985; Amended by Stats. 1992, Ch. 1200.)
65940.5. Waivers of time limits
(a) No list compiled pursuant to Section 65940 shall include an extension or waiver of the time periods prescribed by this chapter within which a state or local agency shall act upon an application for a development project.
(b) No application shall be deemed incomplete for lack of a waiver of time periods prescribed by this chapter within which a state or local government agency shall act upon the application.
(c) Except for the extension *** of the time limits pursuant to Sections 65950.1 ***, no public agency shall require an extension or waiver of the time limits contained in this chapter as a condition of accepting or processing the application for a development project.
(Added by Stats. 1986, Ch. 396; Amended by Stats. 1993, Ch. 1068; Amended by Stats. 1998, Ch. 283)
65941. Required criteria for completeness
(a) The information compiled pursuant to Section 65940 shall also indicate the criteria which the agency will apply in order to determine the completeness of any application submitted to it for a development project.
(b) If a public agency is a lead or responsible agency for purposes of the California Environmental Quality Act, Division 13 (commencing with Section 21000) of the Public Resources Code, that criteria shall not require the applicant to submit the informational equivalent of an environmental impact report as part of a complete application, or to otherwise require proof of compliance with that act as a prerequisite to a permit application being deemed complete. However, that criteria may require sufficient information to permit the agency to make the determination required by Section 21080.1 of the Public Resources Code.
(c) Consistent with this chapter, a responsible agency shall, at the request for the applicant, commence processing a permit application for a development project prior to final action on the project by a lead agency to the extent that the information necessary to commence the processing is available. For purposes of this subdivision, "lead agency" and "responsible agency" shall have the same meaning as those terms are defined in Section 21067 of the Public Resources Code and Section 21069 of the Public Resources Code, respectively.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978; Amended by Stats 1993, Ch. 1131.)
65941.5. Application
Each public agency shall notify applicants for development permits of the time limits established for the review and approval of development permits pursuant to Article 3 (commencing with Section 65940) and Article 5(commencing with Section 65950), of the requirements of subdivision (e) of Section 65962.5, and of the public notice distribution requirements under applicable provisions of law. The public agency shall also notify applicants regarding the provisions of Section 65961. The public agency may charge applicants a reasonable fee not to exceed the amount reasonably necessary to provide the service required by this section. If a fee is charged pursuant to this section, the fee shall be collected as part of the application fee charged for the development permit.
(Added by Stats. 1983, Ch. 1263; Amended by Stats. 1987, Ch. 985.)
65942. Revisions
The information and the criteria specified in Sections 65940, 65941, 65941.5 shall be revised as needed so that they shall be current and accurate at all times. Any revisions shall apply prospectively only and shall not be a basis for determining that an application is not complete pursuant to Section 65943 if the application was received before the revision is effective except for revisions for the following reasons resulting from the conditions which were not known and could not have been known by the public agency at the time the application was received:
(a) To provide sufficient information to permit the public agency to make the determination required by Section 21000.1 of the Public Resources Code, as provided by Section 65941.
(b) To comply with the enactment of new or revised federal, state, or local requirements, except for new or revised requirements of a local agency which is also the lead agency.
(Amended by Stats. 1983, Ch. 1263; Amended by Stats. 1987, Ch. 802 and Ch. 803.)
65943. 30-day review period
(a) Not later than 30 calendar days after any public agency has received an application for a development project, the agency shall determine in writing whether the application is complete and shall immediately transmit the determination to the applicant for the development project. If the written determination is not made within 30 days after receipt of the application, and the application includes a statement that it is an application for a development permit, the application shall be deemed complete for purposes of this chapter. Upon receipt of any resubmittal of the application, a new 30-day period shall begin, during which the public agency shall determine the completeness of the application. If the application is determined not to be complete, the agencys determination shall specify those parts of the application which are incomplete and shall indicate the manner in which they can be made complete, including a list and thorough description of the specific information needed to complete the application. The applicant shall submit materials to the public agency in response to the list and description.
(b) Not later than 30 calendar days after receipt of the submitted materials, the public agency shall determine in writing whether they are complete and shall immediately transmit that determination to the applicant. If the written determination is not made within that 30-day period, the application together with the submitted materials shall be deemed complete for purposes of this chapter.
(c) If the application together with the submitted materials are determined not to be complete pursuant to subdivision (b), the public agency shall provide a process for the applicant to appeal that decision in writing to the governing body of the agency or, if there is no governing body, to the director of the agency, as provided by that agency. A city or county shall provide that the right of appeal is to the governing body or, at their option, the planning commission, or both.
There shall be a final written determination by the agency on the appeal not later than 60 calendar days after receipt of the applicants written appeal. The fact that an appeal is permitted to both the planning commission and to the governing body does not extend the 60-day period. Notwithstanding a decision pursuant to subdivision (b) that the application and submitted materials are not complete, if the final written determination on the appeal is not made within that 60-day period, the application with the submitted materials shall be deemed complete for the purposes of this chapter.
(d) Nothing in this section precludes an applicant and a public agency from mutually agreeing to an extension of any time limit provided by this section.
(e) A public agency may charge applicants a fee not to exceed the amount reasonably necessary to provide the service required by this section. If a fee is charged pursuant to this section, the fee shall be collected as part of the application fee charged for the development permit.
(Amended by Stats. 1979, Ch. 1207. Effective October 2, 1979; Amended by Stats. 1984, Ch. 1723. Operative July 1, 1985; Amended by Stats. 1987, Ch. 1985; Amended by Stats. 1989, Ch. 612.)
65943.5. Appeal
(a) Notwithstanding any other provision of this chapter, any appeal pursuant to subdivision (c) of Section 65943 involving a permit application to a board, office, or department within the California Environmental Protection Agency shall be made to the Secretary for Environmental Protection.
(b) Notwithstanding any other provision of this chapter, any appeal pursuant to subdivision (c) of Section 65943 involving an application for the issuance of an environmental permit from an environmental agency shall be made to the Secretary for Environmental Protection under either of the following circumstances:
(1) The environmental agency has not adopted an appeals process pursuant to subdivision (c) of Section 65943.
(2) The environmental agency declines to accept an appeal for a decision pursuant to subdivision (c) of Section 65943.
(c) For purposes of subdivision (b), "environmental permit" has the same meaning as defined in Section 71012 of the Public Resources Code, and "environmental agency" has the same meaning as defined in Section 71011 of the Public Resources Code, except that "environmental agency" does not include the agencies described in subdivisions (c) and (h) of Section 71011 of the Public Resources Code.
(Added by Stats. 1993, Ch. 419.)
65944. Agency acceptance of applications
(a) After a public agency accepts an application as complete, the agency shall not subsequently request of an applicant any new or additional information which was not specified in the list prepared pursuant to Section 65940. The agency may, in the course of processing the application, request the applicant to clarify, amplify, correct, or otherwise supplement the information required for the application.
(b) The provisions of subdivision (a) shall not be construed as requiring an applicant to submit with his or her initial application the entirety of the information which a public agency may require in order to take final action on the application. Prior to accepting an application, each public agency shall inform the applicant of any information included in the list prepared pursuant to Section 65940 which will subsequently be required from the applicant in order to complete final action on the application.
(c) This section shall not be construed as limiting the ability of a public agency to request and obtain information which may be needed in order to comply with the provisions of Division 13 (commencing with Section 21000) of the Public Resources Code.
(Amended by Stats. 1982, Ch. 84.)
65945. Applicants request for notification at proposed land use action
(a) At the time of filing an application for a development permit with a city or county, the city or county shall inform the applicant that he or she may make a written request to receive notice from the city or county of a proposal to adopt or amend any of the following plans or ordinances:
(1) A general plan.
(2) A specific plan.
(3) A zoning ordinance.
(4) An ordinance affecting building permits or grading permits.
The applicant shall specify, in the written request, the types of proposed action for which notice is requested. Prior to taking any of those actions, the city or county shall give notice to any applicant who has requested notice of the type of action proposed and whose development project is pending before the city or county if the city or county determines that the proposal is reasonably related to the applicants request for the development permit. Notice shall be given only for those types of actions which the applicant specifies in the request for notification.
The city or county may charge the applicant for a development permit, to whom notice is provided pursuant to this subdivision, a reasonable fee not to exceed the actual cost of providing that notice. If a fee is charged pursuant to this subdivision, the fee shall be collected as part of the application fee charged for the development permit.
(b) As an alternative to the notification procedure prescribed by subdivision (a), a city or county may inform the applicant at the time of filing an application for a development permit that he or she may subscribe to a periodically updated notice or set of notices from the city or county which lists pending proposals to adopt or amend any of the plans or ordinances specified in subdivision (a), together with the status of the proposal and the date of any hearings thereon which have been set.
Only those proposals which are general, as opposed to parcel-specific in nature, and which the city or county determines are reasonably related to requests for development permits, need be listed in the notice. No proposals shall be required to be listed until such time as the first public hearing thereon has been set. The notice shall be updated and mailed at least once every six weeks; except that a notice need not be updated and mailed until a change in its contents is required.
The city or county may charge the applicant for a development permit, to whom notice is provided pursuant to this subdivision, a reasonable fee not to exceed the actual cost of providing that notice, including the costs of updating the notice, for the length of time the applicant requests to be sent the notice or notices.
(Added by Stats. 1983, Ch. 1263.)
65945.3. Applicants request for notification of proposed action on local permit process
At the time of filing an application for a development permit with a local agency, other than a city or county, the local agency shall inform the applicant that he or she may make a written request to receive notice of any proposal to adopt or amend a rule or regulation affecting the issuance of development permits.
Prior to adopting or amending any such rule or regulation, the local agency shall give notice to any applicant who has requested such notice and whose development project is pending before the agency if the local agency determines that the proposal is reasonably related to the applicants request for the development permit.
The local agency may charge the applicant for a development permit, to whom notice is provided pursuant to this section, a reasonable fee not to exceed the actual cost of providing that notice. If a fee is charged pursuant to this section, the fee shall be collected as part of the application fee charged for the development permit.
(Added by Stats. 1983, Ch. 1263.)
65945.5. Applicants request for notification of proposed action on state permit process
At the time of filing an application for a development permit with a state agency, the state agency shall inform the applicant that he or she may make a written request to receive notice of any proposal to adopt or amend a regulation affecting the issuance of development permits and which implements a statutory provision.
Prior to adopting or amending any such regulation, the state agency shall give notice to any applicant who has requested such notice and whose development project is pending before the state agency if the state agency determines that the proposal is reasonably related to the applicants request for the development permit.
(Added by Stats. 1983, Ch. 1263.)
65945.7. Error in procedures
No action, inaction, or recommendation regarding any ordinance, rule, or 65945.3, or 65945.5 by any legislative body, administrative body, or the officials of any state or local agency shall be held void or invalid or be set aside by any court on the ground of any error, irregularity, informality, neglect or omission (hereinafter called "error") as to any matter pertaining to notices, records, determinations, publications or any matters of procedure whatever, unless after an examination of the entire case, including evidence, the court shall be of the opinion that the error complained of was prejudicial, and that by reason of such error the party complaining or appealing sustained and suffered substantial injury, and that a different result would have been probable if such error had not occurred or existed. There shall be no presumption that error is prejudicial or that injury was done if error is shown.
(Added by Stats. 1983, Ch. 1263.)
65946. (Repealed by Stats. 1993, Ch. 56)
65950. Time limits for lead agency
(a) Any public agency that is the lead agency for a development project shall approve or disapprove the project within whichever of the following periods is applicable:
(1) *** One hundred eighty days from the date of certification by the lead agency of the environmental impact report if an environmental impact report is prepared pursuant to Section 21100 or 21151 of the Public Resources Code for the development project.
(2) Ninety *** days from the date of certification *** by the lead agency of the environmental impact report if an environmental impact report is prepared pursuant to Section 21100 or 21151 of the Public Resources Code for *** the development project and all of the following conditions are met: ***
(A) The development project is affordable to very low or low-income households, as defined in Sections 50105 and 50079.5 of the Health and Safety Code, respectively. ***
(B) Prior to the application being deemed complete for the development project pursuant to Article 3 (commencing with Section 65940), the lead agency received written notice from the project applicant that an application has been made or will be made for an allocation or commitment of financing, tax credits, bond authority, or other financial assistance from a public agency or federal agency, and the notice specifies the financial assistance that has been applied for or will be applied for and the deadline for application for that assistance, the requirement that one of the approvals of the development project by the lead agency is a prerequisite to the application for or approval of the application for financial assistance, and that the financial assistance is necessary for the project to be affordable as required pursuant to subparagraph (A). ***
(C) There is confirmation that the application *** has been made to the public agency or federal agency prior to certification of the environmental impact report.
(3) Sixty days from the date of adoption by the lead agency of the negative declaration if a negative declaration is completed and adopted for the development project.
(4) Sixty days from the determination by the lead agency that the project is exempt from the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) if the project is exempt from the California Environmental Quality Act.
(b) Nothing in this section precludes a project applicant and a public agency from mutually agreeing in writing to an extension of any time limit provided by this section pursuant to Section 65957.
(c) For purposes of this section, "lead agency" and "negative declaration" shall have the same meaning as those terms are defined in Sections 21067 and 21064 of the Public Resources Code, respectively.
(Amended by Stats. 1983. Operative January 1, 1990; Amended by Stats. 1989, Ch. 847; Amended by Stats. 1993, Ch. 1068; Amended by Stats. 1996, Ch. 80; Amended by Stats. 1998, Ch. 283; Amended by Stats. 1999, Ch. 967.)
65950.1. Extension of time
Notwithstanding Section 65950, if there has been an extension of time pursuant to Section 21100.2 or 21151.5 of the Public Resources Code to complete and certify the environmental impact report, the lead agency shall approve or disapprove the project within 90 days after certification of the environmental impact report.
(Added by Stats. 1983, Ch. 1240.)
65951. Waiver of time limits
In the event that a combined environmental impact report-environmental impact statement is being prepared on a development project pursuant to Section 21083.6 of the Public Resources Code, a lead agency *** shall approve or disapprove the *** project within 90 *** days after the combined environmental impact report-environmental impact statement has been completed and adopted.
(Added by Stats. 1977, Ch. 1200; Amended by Stats. 1998, Ch. 283.)
65952. Time limits for responsible agency
(a) Any public agency which is a responsible agency for a development project that has been approved by the lead agency shall approve or disapprove the development project within whichever of the following periods of time is longer:
(1) Within 180 days from the date on which the lead agency has approved the project.
(2) Within 180 days of the date on which the completed application for the development project has been received and accepted as complete by that responsible agency.
(b) At the time a decision by a lead agency to disapprove a development project becomes final, applications for that project which are filed with responsible agencies shall be deemed withdrawn.
(Added by Stats. 1977, Ch. 1200; Amended by Stats. 1988, Ch. 1187.)
65952.1. Time limits for map approval/disapproval
(a) Except as otherwise provided in subdivision (b), where a development project consists of a subdivision pursuant to the Subdivision Map Act (Division 2 (commencing with Section 66410) of Title 7), the time limits established by Sections 65950 and 65952 shall apply to the approval or disapproval of the tentative map, or the parcel map for which a tentative map is not required.
(b) The time limits specified in Sections 66452.1, 66452.2, and 66463 for tentative maps and parcel maps for which a tentative map is not required, shall continue to apply and are not extended by the time limits specified in subdivision (a).
(Added by Stats. 1982, Ch. 87. Effective March 1, 1982; Amended by Stats. 1989, Ch. 847.)
65952.2. Approval or disapproval of project
No public agency shall disapprove an application for a development project in order to comply with the time limits specified in this chapter. Any disapproval of an application for a development project shall specify reasons for disapproval other than the failure to timely act in accordance with the time limits specified in this chapter.
(Added by Stats. 1993, Ch. 1068.)
65953. Maximum limits
All time limits specified in this article are maximum time limits for approving or disapproving development projects. All public agencies shall, if possible, approve or disapprove development projects in shorter periods of time.
(Added by Stats. 1977, Ch. 1200.)
65954. Conflict with federal rules
The time limits established by this article shall not apply in the event that federal statutes or regulations require time schedules which exceed such time limits.
(Added by Stats. 1977, Ch. 1200.)
65955. Inapplicability
The time limits established by this article shall not apply to applications to appropriate water where such applications have been protested pursuant to Chapter 4 (commencing with Section 1330) of Part 2 of Division 2 of the Water Code, or to petitions for changes pursuant to Chapter 10 (commencing with Section 1700) of Part 2 of Division 2 of the Water Code.
(Amended by Stats. 1978, Ch. 1113. Effective September 26, 1978.)
65956. Criteria for approval/disapproval
(a) If any provision of law requires the lead agency or responsible agency to provide public notice of the development project or to hold a public hearing, or both, on the development project and the agency has not provided the public notice or held the hearing, or both, at least 60 days prior to the expiration of the time limits established by Sections 65950 and 65952, the applicant or his or her representative may file an action pursuant to Section 1085 of the Code of Civil Procedure to compel the agency to provide the public notice or hold the hearing, or both, and the court shall give the proceedings preference over all other civil actions or proceedings, except older matters of the same character.
(b) In the event that a lead agency or a responsible agency fails to act to approve or to disapprove a development project within the time limits required by this article, the failure to act shall be deemed approval of the permit application for the development project. However, the permit shall be deemed approved only if the public notice required by law has occurred. If the applicant has provided seven days advance notice to the permitting agency of the intent to provide public notice, then no earlier than 60 days from the expiration of the time limits established by Sections 65950 and 65952, an applicant may provide the required public notice using the distribution information provided pursuant to Section 65941.5. If the applicant chooses to provide public notice, that notice shall include a description of the proposed development substantially similar to the descriptions which are commonly used in public notices by the permitting agency, the location of the proposed development, the permit application number, the name and address of the permitting agency, and a statement that the project shall be deemed approved if the permitting agency has not acted within 60 days. If the applicant has provided the public notice required by this section, the time limit for action by the permitting agency shall be extended to 60 days after the public notice is provided. If the applicant provides notice pursuant to this section, the permitting agency shall refund to the applicant any fees which were collected for providing notice and which were not used for that purpose.
(c) Failure of an applicant to submit complete or adequate information pursuant to Sections 65943 to 65946, inclusive, may constitute grounds for disapproving a development project.
(d) Nothing in this section shall diminish the permitting agencys legal responsibility to provide, where applicable, public notice and hearing before acting on a permit application.
(Amended by Stats. 1982, Ch. 460; Stats. 1987, Ch. 985.)
65956.5. Appeal
(a) Prior to an applicant providing advance notice to an environmental agency of the intent to provide public notice pursuant to subdivision (b) of Section 65956 for action on an environmental permit, the applicant may submit an appeal in writing to the governing body of the environmental agency, or if there is no governing body, to the director of the environmental agency, as provided by the environmental agency, for a determination regarding the failure by the environmental agency to take timely action on the issuance or denial of the environmental permit in accordance with the time limits specified in this chapter.
(b) There shall be a final written determination by the environmental agency on the appeal not later than 60 calendar days after receipt of the applicants written appeal. The final written determination by the environmental agency shall specify both of the following:
(1) The reason or reasons for failing to act pursuant to the time limits in this chapter.
(2) A date by which the environmental agency shall act on the permit application.
(c) Notwithstanding any other provisions of this chapter, any appeal submitted pursuant to subdivision (a) involving an environmental permit from an environmental agency shall be made to the Secretary for Environmental Protection if the environmental agency declines to accept the appeal for a decision pursuant to subdivision (a) or the environmental agency does not make a final written determination pursuant to subdivision (b).
(d) Any appeal submitted pursuant to subdivision (a) involving an environmental permit to a board, office, or department within the California Environmental Protection Agency shall be made to the Secretary for Environmental Protection.
(e) For purposes of this section, "environmental permit" has the same meaning as defined in Section 71012 of the Public Resources Code, and "environmental agency" has the same meaning as defined in Section 71011 of the Public Resources Code, except that "environmental agency" does not include the agencies described in subdivisions (c) and (h) of Section 71011 of the Public Resources Code.
(Added by Stats. 1993, Ch. 419.)
65957. Extension of time limits
The time limits established by Sections 65950, 65950.1, 65951, and 65952 may be extended once upon mutual written agreement of the project applicant and the public agency for a period not to exceed 90 days from the date of extension. No other extension, continuance, or waiver of these time limits either by the project applicant or the lead agency shall be permitted, except as provided in this section and Section 65950.1. Failure of the lead agency to act within these time limits may result in the project being deemed approved pursuant to the provisions of subdivision (b) of Section 65956. ***
(Amended by Stats. 1983, Ch. 1240; Amended by Stats. 1998, Ch. 283)
65957.1. Multiple approvals
In the event that a development project requires more than one approval by a public agency, such agency may establish time limits (1) for submitting the information required in connection with each separate request for approval and (2) for acting upon each such request; provided, however, that the time period for acting on all such requests shall not, in aggregate, exceed those limits specified in Sections 65950 and 65952.
(Added by Stats. 1978, Ch. 1113.)
65957.5. District director's recommendations; appeal
(a) Whenever the director of a Department of Transportation highway district recommends to a public agency considering an application to subdivide real property or to issue a construction permit that the agency impose certain conditions on its approval of the application, the applicant may appeal the district directors recommendation.
(b) The Department of Transportation shall adopt regulations prescribing procedures for effecting an appeal pursuant to subdivision
(a). The appeal shall be made in writing to the Director of Transportation. The directors decision on the appeal shall be rendered within 60 calendar days after receipt of the appeal, and the directors written determination shall be transmitted to the appellant and to the agency to whom the appealed recommendation was made. The adopted regulations shall require the appellant to pay to the department a fee of not more than 50 percent of the estimated administrative cost to the department of conducting the appeal.
(c) The appeal process, including the directors written determination, shall be completed at least 60 days prior to completion of the period of public review for a draft environmental impact report or a negative declaration prescribed by Section 21091 of the Public Resources Code.
(Added by Stats. 1993, Ch. 796.)
65959. Environmental permits
The Legislature hereby finds and declares that the California Environmental Protection Agency was established to enhance the states protection of the environment by, among other things, more effectively coordinating the permit actions of the departments or boards within the agency which issue environmental permits and by ensuring timely responses to applicants for permits in order to reduce costs associated with compliance with the states environmental protection statutes and programs. It is the intent of this article to provide a mechanism by which the California Environmental Protection Agency may further this objective of environmental protection by bringing relevant agencies together to foster the integration of requests for information, promote speedy and cost-effective compliance, and synchronize, to the maximum extent feasible, the environmental permit requirements imposed on applicants by the departments or boards within the agency.
(Added by Stats. 1992, Ch. 952.)
65959.1. Environmental permit
For purposes of this article, "environmental permit" means any permit issued by the Department of Toxic Substances Control for the storage, treatment, handling, or disposal of hazardous waste, as defined in Section 25117 of the Health and Safety Code, or any waste discharge requirements issued by the State Water Resources Control Board or a California regional water quality control board.
(Added by Stats. 1992, Ch. 952.)
65959.2. Permitting team
(a) At the request of an applicant for more than one environmental permit, the Secretary for Environmental Protection may, using existing staff and budgetary resources, convene a permitting team for the project composed of permit writers and other appropriate personnel from the board or department responsible for review of the project and the issuance of an environmental permit. The permitting team shall identify all statutory and regulatory requirements for the issuance of the environmental permits and provide that information to the applicant in order to facilitate, to the maximum extent feasible, the uniform, consistent, and expeditious processing of environmental permit applications.
(b) At the request of the applicant, the Secretary for Environmental Protection may solicit the participation of relevant federal, state, and local agencies on the permitting team to facilitate cooperation, reduce duplication, and assist in conflict resolution.
(Added by Stats. 1992, Ch. 952.)
65959.3. Authority
This article does not confer any new or additional authority over the issuance of environmental permits on the California Environmental Protection Agency or diminish in any way the existing authority of any other state or local agency.
(Added by Stats. 1992, Ch. 952.)
65960. Geothermal projects
Notwithstanding any other provision of law, if any person applies for approval of a geothermal field development project, then only one permit from the lead agency and one permit from each responsible agency shall be required for all drilling, construction, operation, and maintenance activities required during the course of the productive life of the project, including, but not limited to, the drilling of makeup wells, redrills, well cleanouts, pipeline hookups, or any other activity necessary to the continued supply of geothermal steam to a powerplant. The lead agency and each responsible agency may approve such permits for less than full field development if the applicant submits such an application. Such permits shall include (1) any conditions or stipulations deemed necessary by the lead or responsible agency, including appropriate mitigation measures within the statutory jurisdiction of such agency, and (2) a monitoring program capable of assuring the permittees conformance with all such conditions or stipulations. This section shall not apply to any permit whose issuance is a ministerial act by the permitting agency.
(Added by Stats. 1978, Ch. 1271.)
65961. Building permit requirements
Notwithstanding any other provision of law, upon approval or conditional approval of a tentative map for a subdivision of single- or multiple-family residential units, or upon recordation of a parcel map for such a subdivision for which no tentative map was required, during the five year period following recordation of the final map or parcel map for the subdivision, a city, county, or city and county shall not require as a condition to the issuance of any building permit or equivalent permit for such single- or multiple-family residential units, conformance with or the performance of any conditions that the city or county could have lawfully imposed as a condition to the previously approved tentative or parcel map. Nor shall a city, county, or city and county withhold or refuse to issue a building permit or equivalent permit for failure to conform with or perform any conditions that the city, county, or city and county could have lawfully imposed as a condition to the previously approved tentative or parcel map. However, the provisions of this section shall not prohibit a city, county, or city and county from doing any of the following:
(a) Imposing conditions or requirements upon the issuance of a building permit or equivalent permit which could have been lawfully imposed as a condition to the approval of a tentative or parcel map if the local agency finds it necessary to impose the condition or requirement for any of the following reasons:
(1) A failure to do so would place the residents of the subdivision or of the immediate community, or both, in a condition perilous to their health or safety, or both.
(2) The condition is required in order to comply with state or federal law.
(b) Withholding or refusing to issue a building permit or equivalent permit if the local agency finds it is required to do so in order to comply with state or federal law.
(c) Assuring compliance with the applicable zoning ordinance.
(d) This section shall also apply to a city or city and county which incorporates on or after January 1, 1985, and which includes within its boundaries any areas included in the tentative or parcel map described in this section.
When the incorporation includes areas included in the tentative or parcel map described in this section, "a condition that the city could have lawfully imposed as a condition to the previously approved tentative or parcel map," as used in this section, refers to conditions the county could have imposed had there been no incorporation.
(Added by Stats. 1982, Ch. 1449; Amended by Stats. 1984, Ch. 504; Amended by Stats. 1987, Ch. 193.)
Note: Stats. 1982, Ch. 1449, also reads:
SEC. 4. With the exception of those provisions of this act which may be declarative of existing law, the provisions of this act shall operate only prospectively and shall not apply to tentative maps or parcel maps for which no tentative map was required, which were approved, conditionally approved, or disapproved prior to July 1, 1983.
65962. (Repealed by Stats. 1990, Ch. 1572.)
65962.5. List relating to hazardous waste
(a) The Department of Toxic Substances Control shall compile and update as appropriate, but at least annually, and shall submit to the Secretary for Environmental Protection, a list of all of the following:
(1) All hazardous waste facilities subject to corrective action pursuant to Section 25187.5 of the Health and Safety Code.
(2) All land designated as hazardous waste property or border zone property pursuant to Article 11 (commencing with Section 25220) of Chapter 6.5 of Division 20 of the Health and Safety Code.
(3) All information received by the Department of Toxic Substances Control pursuant to Section 25242 of the Health and Safety Code on hazardous waste disposals on public land.
(4) All sites listed pursuant to Section 25356 of the Health and Safety Code.
(5) All sites included in the Abandoned Site Assessment Program.
(b) The State Department of Health Services shall compile and update as appropriate, but at least annually, and shall submit to the Secretary for Environmental Protection, a list of all public drinking water wells which contain detectable levels of organic contaminants and that are subject to water analysis pursuant to Section 116395 of the Health and Safety Code.
(c) The State Water Resources Control Board shall compile and update as appropriate, but at least annually, and shall submit to the Secretary for Environmental Protection, a list of all of the following:
(1) All underground storage tanks for which an unauthorized release report is filed pursuant to Section 25295 of the Health and Safety Code.
(2) All solid waste disposal facilities from which there is a migration of hazardous waste and for which a California regional water quality control board has notified the Department of Toxic Substances Control pursuant to subdivision (e) of Section 13273 of the Water Code.
(3) All cease and desist orders issued after January 1, 1986, pursuant to Section 13301 of the Water Code, and all cleanup or abatement orders issued after January 1, 1986, pursuant to Section 13304 of the Water Code, which concern the discharge of wastes that are hazardous materials.
(d) The local enforcement agency, as designated pursuant to Section 18051 of Title 14 of the California Code of Regulations, shall compile as appropriate, but at least annually, and shall submit to the California Integrated Waste Management Board, a list of all solid waste disposal facilities from which there is a known migration of hazardous waste. The California Integrated Waste Management Board shall compile the local lists into a statewide list which shall be submitted to the Secretary for Environmental Protection and shall be available to any person who requests the information.
(e) The Secretary for Environmental Protection shall consolidate the information submitted pursuant to this section and distribute it in a timely fashion to each city and county in which sites on the lists are located. The secretary shall distribute the information to any other person upon request. The secretary may charge a reasonable fee to persons requesting the information, other than cities, counties, or cities and counties, to cover the cost of developing, maintaining, and reproducing and distributing the information.
(f) Before a lead agency accepts as complete an application for any development project which will be used by any person, the applicant shall consult the lists sent to the appropriate city or county and shall submit a signed statement to the local agency indicating whether the project and any alternatives are located on a site that is included on any of the lists compiled pursuant to this section and shall specify any list. If the site is included on a list, and the list is not specified on the statement, the lead agency shall notify the applicant pursuant to Section 65943. The statement shall read as follows:
HAZARDOUS WASTE AND SUBSTANCES STATEMENT
The development project and any alternatives proposed in this application are contained on the lists compiled pursuant to Section 65962.5 of the Government Code. Accordingly, the project applicant is required to submit a signed statement that contains the following information:
Name of applicant:
Address:
Phone number:
Address of site (street name and number if available, and ZIP Code):
Local agency (city/county):
Assessor's book, page, and parcel number:
Specify any list pursuant to Section 65962.5 of the Government Code:
Regulatory identification number:
Date of list:
[signed] Applicant, date
(g) The changes made to this section by the act amending this section, that takes effect January 1, 1992, apply only to projects for which applications have not been deemed complete on or before January 1, 1992, pursuant to Section 65943.
(Added by Stats. 1986, Ch. 1048; Amended by Stats. 1990, Ch. 537; Amended by Stats. 1991, Ch. 1212; Amended by Stats. 1996, Ch. 1023. Effective September 29, 1996.)
65963.1. Land use decisions or permits for hazardous waste facilities
Except as otherwise provided in Article 8.7 (commencing with Section 25199) of Chapter 6.5 of Division 20 of the Health and Safety Code, this chapter applies to the making of a land use decision or the issuance of a permit for a hazardous waste facility project by a public agency, as defined in Section 25199.1 of the Health and Safety Code, including, but not limited to, all of the following actions:
(a) The approval of land use permits and conditional use permits, the granting of variances, the subdivision of property, and the modification of existing property lines pursuant to this division or Division 2 (commencing with Section 66410) of Title 7, and, for purposes of this chapter, "project" includes an activity requiring any of those actions.
(b) The issuance of hazardous waste facility permits by the State Department of Health Services pursuant to Chapter 6.5 (commencing with Section 25100) of Division 20 of the Health and Safety Code.
(c) The issuance of waste discharge requirements by California regional water quality control boards pursuant to Article 4 (commencing with Section 13260) of Chapter 4 of Division 7 of the Water Code.
(d) The issuance of authority to construct permits by the district board of an air pollution control district or an air quality management district pursuant to Division 26 (commencing with Section 39000) of the Health and Safety Code.
(e) The issuance of solid waste facilities permits by the enforcement agency pursuant to Article 2 (commencing with Section 66796.30) of Chapter 3 of Title 7.3.
(Added by Stats. 1986, Ch. 1504.)
65964. Definitions
(a) For the purposes of this section, the following definitions apply:
(1) "Permitting agency" means a city or county, or an air pollution control district, as defined in Section 65926, authorized to issue a permit or other preconstruction authorization to construct a Phase 3 reformulated gasoline project.
(2) "Phase 3 Reformulated Gasoline Project" means a project to construct or modify a facility consisting of processing units or other equipment necessary to produce California Phase 3 Reformulated Gasoline, as required to be produced pursuant to paragraph 6 of Executive Order D-5-99, and that is located within the physical boundaries of an existing oil refinery or terminal.
(b) A permitting agency for a phase 3 reformulated gasoline project shall undertake all reasonable efforts to expedite action on the permit or other authorization with the objective of acting upon the permit or other authorization within 12 months of receiving a completed application for a permit or other authorization, if the permit applicant has made reasonable efforts to cooperate with the permitting agency in expediting the processing of the permit or other authorization.
(c) The permitting agency, or a permit applicant with the concurrence of the permitting agency, may request the State Air Resources Board or the State Energy Resources Conservation and Development Commission, or both agencies, to provide appropriate assistance to the permitting agency to assist that agency in achieving the objective of acting upon the permit or other authorization within 12 months.
(d) Upon receipt of a request made pursuant to subdivision (c), the State Air Resources Board or the State Energy Resources Conservation and Development Commission, or both agencies, shall provide appropriate assistance to a permitting agency with the objective of acting upon a permit for a phase 3 reformulated gasoline project within 12 months.
(e) Nothing in this section shall affect any of the following:
(1) The authority or obligation of a public agency under any law, regulation, or ordinance.
(2) The ability of a public agency to hold a public hearing upon, to comment upon, or to impose conditions upon, a reformulated gasoline project.
(3) The rights or remedies of any party pursuant to any law, regulation, or ordinance.
(f) This section shall remain in effect only until January 1, 2003, and as of that date is repealed, unless a later enacted statute, which is enacted before January 1, 2003, deletes or extends that date.
(Added by Stats. 1999, Ch. 812.)