|
![]() |
Posted with the permission of LexisNexis. WESTERN PLACER CITIZENS FOR AN AGRICULTURAL AND RURAL ENVIRONMENT, Plaintiff and Respondent, v. COUNTY OF PLACER et al., Defendants and Appellants; TEICHERT,
INC., Real Party in Interest and Appellant.
C049364 COURT OF APPEAL OF CALIFORNIA, THIRD APPELLATE DISTRICT 144 Cal. App. 4th 890; 50 Cal. Rptr. 3d 799;
2006 Cal. App. LEXIS 1767; 2006 Cal. Daily Op. Service 10396; 2006
Daily Journal DAR 14839 November 9, 2006, Filed SUBSEQUENT HISTORY: Modified and rehearing denied
by Western Placer Citizens for an Agricultural & Rural Environment v.
County of Placer, 2006 Cal. App. LEXIS 1928 (Cal. App. 3d Dist., Dec. 11, 2006) PRIOR HISTORY: [***1]
Superior Court of Placer County, No. SCV15349, James W. Luther, Judge.
(Retired judge of the Mendocino Sup. Ct. assigned by the Chairperson of the
Judicial Council.) SUMMARY: CALIFORNIA OFFICIAL REPORTS
SUMMARY In a
challenge to a final environmental impact report (FEIR) by an environmental
group, the trial court directed a county to set aside its approval of a
proposed aggregate mine and its certification of the FEIR. The trial court
found that the county violated the California Environmental Quality Act (CEQA)
(Pub. Resources Code, § 21000 et seq.)
by failing to include and analyze a slightly revised project description
submitted by the applicant after the FEIR was prepared and by inadequately
analyzing water supply issues. (Superior Court of Placer County, No. SCV15349,
James W. Luther, Judge.*) * Retired
judge of the Mendocino Superior Court, assigned by the Chief Justice pursuant
to article VI, section 6 of the California Constitution. The Court
of Appeal reversed the decision of the trial court, holding that CEQA does not
require a lead agency to revise an FEIR to include any new information or
project changes that arise after the environmental impact report (EIR) is released
but prior to certification, before the agency determines whether the
information is significant enough to require that the EIR be recirculated.
Turning to the question of evidentiary sufficiency, which was unaddressed by
the trial court, the court found that substantial evidence supported the
county's determination that new phasing was not significant new information
requiring revision and recirculation of the EIR. The record supported a
conclusion that the revised phasing created no new impacts from what was
already discussed in the FEIR, and CEQA did not require the county to delay the
project further in order to evaluate the new project's reduced impacts on the
environment. The court also agreed with the applicant that the trial court
erred in its finding about water supply. Contrary to the trial court's factual
conclusion, there were multiple sources of water available to the property. The
EIR identified existing, available, and sufficient sources of water for the
project and in that respect was sufficient. An EIR need not identify a
guaranteed source of water. (Opinion by Nicholson, J., with Scotland, P. J.,
and Butz, J., concurring.) [*891]
HEADNOTES: CALIFORNIA OFFICIAL REPORTS
HEADNOTES Classified to California Digest of Official
Reports (1) Pollution and
Conservation Laws § 2--California
Environmental Quality Act--Impact Reports--Purpose.--The environmental impact
report (EIR) is the heart of the California Environmental Quality Act (CEQA) (Pub.
Resources Code, § 21000 et seq.)
(Guidelines for the Implementation of CEQA, Cal. Code Regs., tit. 14, § 15003, subd. (a)). Its purpose is to
inform the public and its responsible officials of the environmental
consequences of their decisions before they are made. Thus, the EIR protects
not only the environment but also informed self-government. To this end, public
participation is an essential part of the CEQA process. (2) Pollution and
Conservation Laws § 2.3--California
Environmental Quality Act--Impact Reports--Sufficiency--Description--Revisions.--A description of a project
is an indispensable component of a valid environmental impact report (EIR). An
accurate, stable and finite project description is the sine qua non of an
informative and legally sufficient EIR. The defined project and not some
different project must be the EIR's bona fide subject. The reporting process
under the California Environmental Quality Act (CEQA) (Pub. Resources Code,
§ 21000 et seq.) is not designed to
freeze the ultimate proposal in the precise mold of the initial project;
indeed, new and unforeseen insights may emerge during investigation, evoking
revision of the original proposal. CEQA requires an EIR to reflect a good faith
effort at full disclosure; it does not mandate perfection, nor does it require
an analysis to be exhaustive. Analysis in an EIR must be specific enough to
permit informed decision making and public participation. The need for thorough
discussion and analysis is not to be construed unreasonably, however, to serve
as an easy way of defeating projects. Absolute perfection is not required. (3) Pollution and
Conservation Laws § 1.2--California
Environmental Quality Act--Construction--Requirements Not Present in Statute.--When interpreting the
California Environmental Quality Act (Pub. Resources Code, § 21000 et seq.), courts are not authorized
to impose requirements not present in the statute. It is the intent of the
Legislature that courts, consistent with generally accepted rules of statutory
interpretation, shall not interpret this division or the state guidelines in a
manner which imposes procedural or substantive requirements beyond those
explicitly stated in this division or in the state guidelines (Pub.
Resources Code, § 21083.1). [*892]
(4) Pollution and
Conservation Laws § 1.2--California
Environmental Quality Act--Construction--Persuasive Authority--Federal Statute.--The court may view the
National Environmental Policy Act (42 U.S.C. § 4321) as persuasive authority when
interpreting the California Environmental Quality Act Pub. Resources Code,
§ 21000 et seq.). (5) Pollution and
Conservation Laws § 2.3--California
Environmental Quality Act--Impact
Reports--Sufficiency--Description--Revisions--Significance of
Information--Aggregate Mine.--A county properly approved a proposed aggregate mine and
certified a final environmental impact report (FEIR), even though the county
failed to include and analyze a slightly revised project description submitted
after the FEIR was prepared, because substantial evidence supported a finding
that new phasing was not significant new information requiring revision and
recirculation. The California Environmental Quality Act (Pub. Resources
Code, § 21000 et seq.) does not
require a lead agency to revise an FEIR to include any new information or
project changes that arise after the environmental impact report (EIR) is released
but prior to certification before the agency determines whether the information
is significant enough to require that the EIR be recirculated. [12 Witkin, Summary of Cal. Law (10th ed. 2005)
Real Property, § 841.] (6) Pollution and
Conservation Laws § 2.3--California
Environmental Quality Act--Impact Reports--Sufficiency--Water.--An environmental impact
report (EIR) need not identify a guaranteed source of water. The EIR should compare
the effects of a project with the actual conditions that exist in the area. COUNSEL: Anthony J. LaBouff, County
Counsel, and Valerie D. Flood, Deputy County Counsel, for Defendants and
Appellants. Taylor & Wiley, John M. Taylor, Jesse J.
Yang and Kate A. Leary for Real Party in Interest and Appellant. Brandt-Hawley Law Group, Susan Brandt-Hawley and
Paige J. Swartley for Plaintiff and Respondent. JUDGES: Nicholson, J., with Scotland,
P. J., and Butz, J., concurring. OPINION BY: Nicholson OPINION: [**802]
NICHOLSON, J.--The superior court determined a county's
environmental impact report analyzing a proposed aggregate mine violated the
California [*893] Environmental Quality Act (Pub. Resources
Code, § 21000 et seq. (CEQA)) by
failing to include and analyze a slightly revised project description submitted
by the applicant after the final environmental impact report was prepared, and
by inadequately analyzing water supply issues. We reverse. FACTS In
December 1994, real party in interest Teichert, Inc. (Teichert), submitted
permit applications for a 100-year project to mine [***2] and process sand, gravel, and granite on 945
acres of a 1,878-acre site located four miles north of Lincoln in
unincorporated Placer County. Coon Creek, a perennial stream, traverses the
central portion of the site and flows south westward. Doty Ravine crosses the
southern tip of the site flowing westward, then joins Coon Creek. The site is
currently operated as a cattle ranch with most of the level land in permanent
pasture, hayfield or livestock food crops, and the remaining land used
primarily as rangeland. The state Department of Conservation has designated
virtually all of the site as prime farmland and farmland of local importance. In
December 1994, defendant County of Placer (County) issued a notice of
preparation of an environmental impact report (EIR). It received numerous
comments and complaints, in particular opposing Teichert's plan to locate the
mine's processing plant near existing residences and to direct truck traffic to
and from the site on narrow, substandard roads abutted by existing residences.
Teichert withdrew its proposal in 1995. Subsequently,
Teichert purchased 1,577 acres west of the original project site. It redesigned
the project in response to many of [***3] the public's concerns. It moved the
processing plant to a remote location away from the residences, provided a
direct truck route to Highway 65 to avoid using existing roads, and increased
setbacks from abutting property owners. In 1996,
Teichert submitted revised permit applications incorporating these changes. The
new proposal called for an 85-year project to mine and reclaim 1,000 acres of
the now 3,455-acre site. Teichert would process 37 million tons of sand and
gravel and 122 million tons of granite. Aggregate mining and reclamation would
occur in nine successive phases, beginning on the site's southwest area (phase
1) and moving in order to the northeast (phases 2-9). [*894] The
County and its consultant released a draft EIR in 1999, more than two years
after Teichert submitted its revised applications. The draft EIR analyzed
several project alternatives, including one that came to be designated as the
"Mitigated Design Alternative." This proposal would reduce the
project's length from 85 years to 40 years and reduce the mining and processing
areas from 1,000 acres to 785 acres. The
County publicly circulated the draft EIR for 100 days, and received numerous
comments. In response, [***4] the County revised 11 chapters of the draft
EIR and six technical appendices. The County then recirculated the revised
chapters and appendices for another 60 days (the revised [**803] draft EIR (RDEIR)), and received additional
comments thereon. Portions
of the land proposed to be mined were covered by California Land Conservation
Act of 1965 (Williamson Act) contracts that would prohibit mining. During 2000
and 2001, Teichert met with County staff regularly to resolve this and other
issues. As a result of such a meeting held in November 2001, Teichert proposed
to implement the Mitigated Design Alternative as its project, except it would
change the phasing. Under the new phasing, mining would occur so as to avoid
mining on those lands affected by the Williamson Act contracts until the
contracts expired. Thus, instead of moving in order from southwest to
northeast, aggregate mining and reclamation in general would begin in the
middle of the site, go back southwest, then jump over the middle and continue
to the northeast, still in nine phases. Using the former phase designations,
mining would begin in former phase 4, proceed northeast to former phase 5, go
back to former phases 3, 2, and 1, then go [***5] northeast again from former phase 6 through
phase 9. The
County released the final EIR (FEIR) on January 21, 2002, some seven years
after Teichert filed its initial application. This document incorporated the
County's responses to the comments received during both circulation periods.
The FEIR mentioned the project could avoid conflicts with the Williamson Act by
delaying mining on those lands affected by Williamson Act contracts. It did
not, however, include a revised description of the project reflecting
Teichert's decision to proceed with that suggestion and change its phasing to
avoid the affected lands, nor did it analyze whether the change in phasing
created additional impacts. Four days
later, January 25, 2002, Teichert submitted a revised project application to
implement the Mitigated Design Alternative project with the [*895]
change to the phasing. A second proposed change involved relocating the
portable processing plant to the site of the permanent plant. Teichert's latest
proposal became known as the Revised Mitigated Design Alternative. Before
the County Planning Commission, plaintiff Western Placer Citizens for an
Agricultural and Rural Environment (WPCARE) and others objected [***6] to the proposed project and the adequacy of
the FEIR on numerous grounds. On November 12, 2002, the planning commission
certified the FEIR and unanimously approved the project. WPCARE
appealed the decision to the board of supervisors (the Board). On December 17,
2002, the Board denied the appeal, approved the revised project, and directed
its staff to prepare findings and conditions of approval. On February 4, 2003,
the Board formally approved the project. WPCARE
filed a petition for writ of mandate, alleging the County's review of the
project violated CEQA in numerous respects. The trial court disagreed with
WPCARE on all but two grounds. It concluded the FEIR violated CEQA by (1) not
describing the Revised Mitigated Design Alternative project with its new
phasing; and (2) inadequately analyzing the availability of a long-term water
supply. The court ordered a writ of mandate issue directing the County to set
aside its approval of the project and certification of the FEIR, and to refrain
from granting further approvals pending certification of a revised FEIR. Teichert
and the County challenge the trial court's ruling. [**804] DISCUSSION I Standard of Review We review
[***7] the record de novo to
determine whether the County prejudicially abused its discretion in certifying
the FEIR and approving the project. Under CEQA, an abuse of discretion occurs
if the County did not proceed in the manner required by law, its decision was
not adequately supported by findings, or its findings were not supported by
substantial evidence in light of the whole record. (Pub. Resources Code, §
§ 21168, 21168.5.) II Revised Project Description Teichert
argues the trial court erred in determining the FEIR violated CEQA by not
identifying and addressing the new phasing. It claims CEQA [*896]
does not per se require a revised project description be included in the
FEIR itself, and substantial evidence in the record demonstrated the changed
phasing was not significant new information requiring additional analysis in,
or recirculation of, the FEIR. We agree with Teichert. A. Additional background information WPCARE
complained about the new project description not being included in the FEIR for
further review. Responding to the complaints, County staff noted it had
distributed Teichert's new project description [***8] to the public at the Rural Lincoln Municipal
Advisory Council on February 4, 2002, as part of a document it called a
supplemental entitlement detail. The County asserted there was no requirement
for a public review of the supplemental entitlement detail "because it
serves as the project description upon which the staff prepares their
recommendations." County
staff agreed there were changes between the Revised Mitigated Design
Alternative and the Mitigated Design Alternative, but "[i]n all cases the
changes reflect an improvement in the environmental condition when compared to
the original project or the mitigated design alternatives." Staff
stated no further modification of the FEIR was required because the FEIR
adequately analyzed the project and its impacts. The changes incorporated into
the final proposed project "meet the intent of CEQA (i.e., lessening or
eliminating environmental impacts) and show responsiveness to the issues
raised." A new draft EIR was not required because the "proposed
project is, in all substantive respects, identical to the mitigated design
alternative which was examined in the FEIR. The mitigated design alternative
was specifically selected as the project [***9] description because of its ability to reduce
and/or eliminate significant effects." Approving
the project, the Board found the project "as approved is a modification of
the mitigated design alternative that was considered in the FEIR. The
modifications to the mitigated design alternative does [sic] not result
in any additional impacts that were not analyzed in the FEIR." The trial
court, however, concluded the Board could not make that finding without first
including the new phasing in the EIR: "In their arguments, the parties
treat the new phasing as raising a single question: [P] Was the new [*897]
phasing ' significant new information' as defined in Guideline
15088.5(a), requiring that it be added to the RDEIR and that the RDEIR be
recirculated before certification of the FEIR[?] "But
it really raises two questions: [P] 1. Was the new phasing 'new information'
that was required to be added to the [**805] RDEIR? [P] 2. If so, was it 'significant' new
information, requiring that the RDEIR be recirculated before certification of
the FEIR? "The
answer to the first question is yes: As part of Teichert's revised project
description, the new phasing was information that CEQA requires to [***10] be identified and addressed in the EIR
itself. [Citations.] "The
answer to the second question is unknown: Whether new information about a
project is 'significant' depends on whether failure to recirculate an EIR
containing the new information would deprive the public of a meaningful opportunity
to comment upon a substantial adverse environmental effect of the project.
[CEQA] Guideline 15088.5(a). "By
the express terms of [CEQA] Guideline 15088.5, the question of whether
to recirculate a published EIR does not arise until the new information is
added to the EIR. CEQA requires that the question of any substantial new
impacts be identified, addressed, assessed, and resolved in the EIR itself.
[Citations.] Only then can the test in Guideline 15088.5(a) be applied
and the decision whether recirculation is required be made. "When
it certified the FEIR, the Board of Supervisors found that the new aggregate
mining and reclamation phasing would not result in any additional impacts that
were not analyzed in the FEIR. Without a description and analysis of the new
phasing in the FEIR, there was no substantial evidence to support this
finding." B. Exhaustion of administrative remedies Teichert [***11] initially asserts WPCARE failed to exhaust
its administrative remedies on this issue. Teichert claims WPCARE argued the
FEIR was inadequate only because the revised phasing was significant new
information which CEQA requires be recirculated in a revised EIR. Teichert
argues WPCARE failed to exhaust by not arguing for the rule announced by the
trial court, that all new information must be included in an EIR whether or not
it is significant. [*898] We
disagree with Teichert's argument. Less specificity is required to preserve an
issue for appeal from an administrative hearing than from a judicial hearing. (Coalition
for Student Action v. City of Fullerton (1984) 153 Cal. App. 3d 1194, 1197 [200
Cal. Rptr. 855].) WPCARE's arguments fairly apprised the County, Teichert,
and the trial court it believed the FEIR was legally inadequate because the
project description did not include the changed phasing and the document did
not discuss whether the new phasing created unaddressed environmental impacts.
This was sufficient to satisfy the requirements of CEQA. (East Peninsula Ed.
Council, Inc. v. Palos Verdes Peninsula Unified School Dist. (1989) 210 Cal.
App. 3d 155, 175-177 [258 Cal. Rptr. 147].) [***12] Having
found the issue sufficiently raised, we need not address Teichert's claim the
trial court erred by addressing an issue on its own volition. C. Including all new information in the FEIR
(1) The EIR is the "heart of
CEQA." (Guidelines, § 15003,
subd. (a); n1 see Laurel Heights Improvement Assn. v. Regents of
University of California (1988) 47 Cal.3d 376, 392 [253 Cal. Rptr. 426, 764
P.2d 278] (Laurel Heights I).) "Its purpose is to inform the
public and its responsible [**806] officials of the environmental consequences
of their decisions before they are made. Thus, the EIR 'protects not
only the environment but also informed self-government.' [Citation.]" (Citizens
of Goleta Valley v. Board of Supervisors (1990) 52 Cal.3d 553, 564 [276 Cal.
Rptr. 410, 801 P.2d 1161] (Goleta Valley), original italics.)
"To this end, public participation is an 'essential part of the CEQA process.'
[Citations.]" (Laurel Heights Improvement Assn. v. Regents of
University of California (1993) 6 Cal.4th 1112, 1123 [26 Cal. Rptr. 2d 231, 864
P.2d 502] (Laurel Heights II).) n1 All
references to "Guidelines" are to the state CEQA Guidelines, which
implement the provisions of CEQA. (Cal. Code Regs., tit. 14, § 15000.) [***13]
(2) A description of the project
is an indispensable component of a valid EIR. "We reiterate--an accurate,
stable and finite project description is the sine qua non of an
informative and legally sufficient EIR. The defined project and not some
different project must be the EIR's bona fide subject. The CEQA reporting
process is not designed to freeze the ultimate proposal in the precise mold of
the initial project; indeed, new and unforeseen insights may emerge during investigation,
evoking revision of the original proposal." (County of Inyo v. City of
Los Angeles (1977) 71 Cal. App. 3d 185, 199-200 [139 Cal. Rptr. 396].) [*899]
"CEQA
requires an EIR to reflect a good faith effort at full disclosure; it does not
mandate perfection, nor does it require an analysis to be exhaustive." (Kings
County Farm Bureau v. City of Hanford (1990) 221 Cal. App. 3d 692, 712 [270
Cal. Rptr. 650].) Analysis in an EIR "must be specific enough to
permit informed decision making and public participation. ... The need for
thorough discussion and analysis is not to be construed unreasonably, however,
to serve as an easy way of defeating projects. 'Absolute perfection is not [***14] required ... .' [Citations.]" (Laurel
Heights I, supra, 47 Cal.3d at p. 406.) (3) When interpreting CEQA,
courts are not authorized to impose requirements not present in the statute.
"It is the intent of the Legislature that courts, consistent with
generally accepted rules of statutory interpretation, shall not interpret this
division or the state guidelines ... in a manner which imposes procedural or
substantive requirements beyond those explicitly stated in this division or in
the state guidelines." (Pub. Resources Code, § 21083.1.) The trial
court determined the EIR had to be revised to include the changes made to the
project before the County determined whether the changes were significant
enough to require recirculation. The authority the court cited to support its
holding does not expressly do so. The parties have directed us to no provision
in CEQA or the Guidelines, and we have found none, that requires all changes
made to a project after the final EIR is released but prior to certification to
be included in the EIR. The
closest CEQA comes to addressing this issue is when it discusses the
requirement to recirculate an EIR. [***15] The relevant provision of CEQA, section
21092.1, reads in part: "When significant new information is added to
an environmental impact report after notice has been given pursuant to Section
21092 [notice of availability of draft EIR for public review] and
consultation has occurred pursuant to Sections 21104 and 21153,
but prior to certification, the public agency shall give notice again pursuant
to Section 21092, and consult again pursuant to Sections 21104
and 21153 before certifying the environmental impact report." (Pub.
Resources Code, § 21092.1.) The
Guidelines clarify this directive as follows: [**807]
" (a) A lead agency is required to recirculate an EIR when
significant new information is added to the EIR after public notice is given of
the availability of the draft EIR for public review under [Guidelines] Section
15087 but before certification. As used in this section, the term 'information'
can include changes in the project or environmental setting as well as
additional data or [*900] other information. New information added to
an EIR is not 'significant' unless the EIR is changed in a way that deprives
the public of a meaningful opportunity to comment [***16] upon a substantial adverse environmental
effect of the project or a feasible way to mitigate or avoid such an effect
(including a feasible project alternative) that the project's proponents have
declined to implement. 'Significant new information' requiring recirculation
includes, for example, a disclosure showing that: "(1)
A new significant environmental impact would result from the project or from a
new mitigation measure proposed to be implemented. "(2)
A substantial increase in the severity of an environmental impact would result
unless mitigation measures are adopted that reduce the impact to a level of
insignificance. "(3)
A feasible project alternative or mitigation measure considerably different
from others previously analyzed would clearly lessen the significant
environmental impacts of the project, but the project's proponents decline to
adopt it. "(4)
The draft EIR was so fundamentally and basically inadequate and conclusory in
nature that meaningful public review and comment were precluded. (Mountain
Lion Coalition v. Fish & Game Com. (1989) 214 Cal. App. 3d 1043 [263 Cal.
Rptr. 104].) "(b)
Recirculation is not required where the new information added [***17] to the EIR merely clarifies or amplifies or
makes insignificant modifications in an adequate EIR. "(c)
If the revision is limited to a few chapters or portions of the EIR, the lead
agency need only recirculate the chapters or portions that have been modified.
[P] ... [P] "(e)
A decision not to recirculate an EIR must be supported by substantial evidence
in the administrative record." (Guidelines, § 15088.5.) Thus, the
statute and Guidelines explain what to do when significant information is added
to an EIR, but they do not address whether an agency must add all information
to an EIR before determining whether the information is significant and
triggers recirculation. [*901] The
California case closest to addressing the issue, Chaparral Greens v. City of
Chula Vista (1996) 50 Cal.App.4th 1134 [58 Cal. Rptr. 2d 152] (Chaparral
Greens), implies not all new information must be added to the EIR. There, a
developer proposed a massive residential development on a large tract of land
in San Diego County. The land included [**808] coastal sage scrub habitat and more than 80
varieties of sensitive, threatened or endangered plant and animal species. It
was within an area addressed by two regional [***18] conservation planning programs being
developed by the county. (Id. at pp. 1139-1140.) After the
final EIR was issued jointly by the City of Chula Vista and the county, the
county developed new information as part of its conservation planning programs
that established the tract's importance in regional multispecies preservation
efforts. The county, along with federal and state agencies, also proposed
restricting loss of coastal sage scrub habitat due to development to five
percent within any one subregion. (Chaparral Greens, supra, 50 Cal.App.4th
at pp. 1140-1141.) During
administrative hearings on the proposed project, a number of people argued the
EIR needed to be revised and recirculated to reflect these new developments.
The city and county did not revise or recirculate the EIR. The plaintiffs sued,
claiming the local agencies violated CEQA by failing to consider the new
information. The trial court denied the plaintiffs' petition for writ of
mandate, and the Court of Appeal affirmed. (Chaparral Greens, supra, 50
Cal.App.4th at pp. 1141-1142, 1154.) "The
question here," the appellate court wrote, "is whether Respondents'
implicit decision [***19] not to
recirculate the [EIR] (i.e., the decision that the new information was not
'significant') was supported by substantial evidence. (Laurel Heights II,
supra, 6 Cal.4th at pp. 1132-1135.) Although Chaparral Greens urges this
court to undertake an independent review of this issue, its position is
untenable. Only the addition of significant new information triggers the
need for recirculation under section 21092.1 and thus the agency's first
obligation is to determine whether the new information meets this statutory
requirement. In this context, a procedural violation cannot exist 'unless the
[agency's] decision regarding the significance of the new information fails to
pass muster under the [substantial evidence] standard of review.' (Laurel
Heights II, supra, 6 Cal.4th at p. 1134.)" (Chaparral Greens,
supra, 50 Cal.App.4th at p. 1147, original italics.) The court
reviewed the new information which was contained in the administrative record
but not the EIR, and concluded substantial evidence [*902]
supported the local agencies' determination that the information was not
"significant" within the meaning of CEQA. The [***20] agencies' decision not to revise the EIR and
recirculate was appropriate. (Chaparral Greens, supra, 50 Cal.App.4th at pp.
1148, 1151.) Nowhere did the court fault the agencies for determining the
information was not significant without first including the information in the
EIR. It stated the local agencies did not violate CEQA by not revising the EIR
and recirculating it. The
approach taken by the agencies in Chaparral Greens was consistent with
an approach upheld by the Supreme Court in Goleta Valley, supra, 52 Cal.3d
553. There, opponents of an oceanfront resort hotel argued a supplemental
EIR failed to consider a reasonable range of alternative sites to the project.
The planning commission certified the EIR, and the opponents appealed the
decision to the county board of supervisors. Prior to hearings before the
board, the opponents submitted a letter urging the county to consider seven
additional sites in another supplemental EIR. (Id. at pp. 561-562, 567.) After
hearings, the board filed the EIR without revising it, approved the project,
and adopted findings. The findings included the county's analysis and
determination [***21] that none
of the opponents' suggested new sites were feasible alternative sites. On
appeal, the opponents claimed the county violated CEQA by not including this
analysis in the EIR. (Goleta Valley, supra, 52 Cal.3d at pp. 562-563, 568.) The
Supreme Court concluded the county did not violate CEQA by not including its
analysis in the EIR. Due to the timing of the opponents' letter well after the
public [**809] comment period expired, the county did not abuse
its discretion by explaining its reasons for rejecting the sites by means of
administrative findings rather than another EIR. (Goleta Valley, supra, 52
Cal.3d at pp. 568-570.) These
cases indicate all new information occurring after release of the final EIR but
prior to certification and project adoption need not be included in the EIR
before the agency determines whether the new information is significant so as
to trigger revision and recirculation. Contrary to CEQA, the trial court in the
case before us imposed a procedural requirement beyond that expressly stated in
the statute or the Guidelines. (4) This conclusion is consistent
with policy underlying the National Environmental Policy Act of 1969 (NEPA), 42
U.S.C. § 4321 [***22] et seq., which [*903]
we may view as persuasive authority when interpreting CEQA. (No Oil,
Inc. v. City of Los Angeles (1974) 13 Cal.3d 68, 86, fn. 21 [118 Cal. Rptr. 34,
529 P.2d 66].) Deciding whether a public agency had to revise and
recirculate an environmental impact statement (EIS) when it selected an
alternative not analyzed in the document, the Ninth Circuit Court of Appeals
observed: "The main policy reason for soliciting public comment is to use
public input in assessing a decision's environmental impact. [Citations.] To
effectuate this purpose, agencies must have some flexibility to modify
alternatives canvassed in the draft EIS to reflect public input. If an agency
must file a supplemental draft EIS every time any modifications occur, agencies
as a practical matter may become hostile to modifying the alternatives to be
responsive to earlier public comment. Moreover, requiring agencies to repeat
the public comment process when only minor modifications are made promises to
prolong endlessly the NEPA review process." (State of Cal. v. Block
(9th Cir. 1982) 690 F.2d 753, 771.) (5) We thus conclude CEQA does
not require a lead agency to revise a final EIR to include [***23] any new information or project changes that
arise after the EIR is released but prior to certification before the agency
determines whether the information is significant enough to require the EIR be
recirculated. This conclusion, however, does not end our analysis. We are now
left with the question the trial court refused to address: Is the County's
determination that the new phasing was not significant new information
requiring revision and recirculation of the EIR supported by substantial
evidence in the record? D. Significance of new information We give
the County's determination substantial deference and presume it to be correct.
WPCARE bears the burden of proving substantial evidence does not support the
County's decision not to revise and recirculate the FEIR. (Sierra Club v.
County of Napa (2004) 121 Cal.App.4th 1490, 1497 [19 Cal. Rptr. 3d 1].) At trial,
WPCARE complained there was no review of potential significant environmental
impacts caused by the change in phasing. It also alleged the change created
confusion, leading, for example, the Department of Conservation to note in a
letter dated March 18, 2002, that the proposed reclamation plan originally
attached to [***24] the FEIR was
no longer based on the actual project being approved. [*904] As noted
above, county staff reviewed the change and determined, and the board found,
the change created no new environmental impacts. Indeed, the County determined
"[i]n all cases the changes reflect an improvement in the environmental
condition when compared to the original
[**810] project or the
mitigated design alternatives." (Italics added.) Mining on lands
encumbered with Williamson Act contracts is delayed, and impacts from having
two processing plant sites are reduced by eliminating the temporary plant site. As we
just determined, CEQA did not require the Board to include that analysis in the
FEIR or even to make a written finding or order to that effect. By certifying
the FEIR, the Board necessarily concluded the new information did not require
recirculation and additional public comment. (Laurel Heights II, supra, 6
Cal.4th at pp. 1133-1134.) Substantial evidence in the record supports that
determination. As for
the confusion over the reclamation plan, the reclamation plan originally
included in the FEIR and submitted to the Department of Conservation was
revised in September 2002, before [***25] the FEIR was certified, to reflect the
project's revised phasing and the relocation of the plant. The revised plan was
submitted to the Department of Conservation for review and comment. The
Department of Conservation made no comment on the revised plan, and the Board
approved it when it approved the project. Thus, whatever inconsistencies
existed between the revised project and the reclamation plan were remedied
before the Board approved the project. By approving the revised reclamation
plan with the project, the Board's findings that the revised phasing was not
significant new information for purposes of CEQA applied equally to the revised
reclamation plan. WPCARE
proffers arguments regarding the effect the new phasing may have on two
specific mitigation measures. WPCARE failed to raise these arguments below, and
thus forfeits them here. (Resource Defense Fund v. Local Agency Formation
Com. (1987) 191 Cal. App. 3d 886, 894 [236 Cal. Rptr. 794].) Were we
to rule on WPCARE's new arguments, we would disagree with each of them. One of
WPCARE's forfeited arguments was raised by the trial court. The entire area to
be mined lies within the 100-year floodplain. The court [***26] suggested a mitigation measure designed to
reduce flooding impacts could have been adversely affected by the revised
phasing. The measure called for a berm to be built around the permanent plant
site to protect the settling ponds from inundation in the event of a flood.
This, however, would eliminate flood storage land for approximately 150
acre-feet of flood water. In response, the FEIR designated the phase 1
excavation as an offsetting storage [*905] area for that water. The court wondered if
the determination to excavate phase 4 first instead of phase 1 removed that
additional storage. The
obvious answer is the pit dug in what was once phase 4 would serve the same
purpose. Indeed, the FEIR indicates phase 4 will create a larger pit than phase
1, resulting in greater flood water storage than originally planned. Had WPCARE
timely raised this argument, the County correctly would have determined this
information did not trigger revision and recirculation of the FEIR. WPCARE's
second forfeited argument concerned possible impacts the new phasing might have
on another mitigation measure. The FEIR concluded one impact from the project
would be the possible uncontrolled overflow of Coon Creek [***27] north of phase 9 into the mining pit during a
flood. Such an uncontrolled flow could result in headcutting of the channel,
erosion of the bank, and possible permanent redirection of the entire Coon
Creek flow into the mining pit. To mitigate this possible impact, the FEIR proposed
Teichert [**811] construct a hardened bank overflow area. This
would allow the creek to overtop its bank and overflow into the mining pit in a
controlled manner without risk of the bank collapsing. A hardened surface would
be built within the existing bank to direct the overflow. The overflow area is
to be constructed before the fourth phase of mining begins. WPCARE
asserts without argument or analysis the change in phasing could impact this
mitigation measure. We do not see how. The possibilities of bank failure are
minimal until the pit approaches the creek in the final phases. Teichert can
still construct the overflow area before it begins phase 4, which will ensure
the improvement exists as the pit moves closer to the creek. That its fourth phase
is now the original phase 2 makes little difference. The pit will still be hundreds
of feet away from the creek at that time, and the last three phases will still
be [***28] done in the order
originally planned. Had WPCARE timely raised this argument also, substantial
evidence would have supported the County's determination that this information
did not trigger revision and recirculation of the FEIR. On this
particular issue, CEQA fulfilled its purpose. Years of environmental review
informed the public and the decision makers of the environmental consequences
of Teichert's proposed mine before it was approved. (See Goleta Valley,
supra, 52 Cal.3d at p. 564.) As a result, both the County and Teichert,
with significant input from the public, were able to work to " '[i]dentify
ways that environmental damage [could] be avoided or significantly reduced.'
" (Berkeley Keep Jets Over the Bay Com. v. Board of Port Comrs. (2001)
91 [*906] Cal.App.4th 1344, 1354 [111 Cal.Rptr. 2d 598],
quoting Guidelines, § 15002.) WPCARE
has failed to satisfy its burden of proof. Substantial evidence supports the
County's decision not to revise and recirculate the FEIR to include the changed
phasing and the relocation of the plant site. The evidence demonstrates the
approved project is more environmentally sensitive than the Mitigated Design
Alternative which was fully analyzed [***29] in the FEIR. The record supports the County's
conclusion the revised phasing created no new impacts from what was already
discussed in the FEIR. CEQA did not require the County to delay the project
further in order to evaluate the new project's reduced impacts on the
environment. III Water Supply Analysis Teichert
argues the trial court erred when it determined no substantial evidence
supported the County's finding there would be sufficient water to supply the
project's needs through its mining life and its reclamation requirements. We
agree with Teichert. In its
decision the trial court noted that Teichert anticipates obtaining water from
the Nevada Irrigation District (NID). The court said: "Teichert's use of
NID water is based on a year-to-year contract, not on priority in time, right,
or proximity. Part of the present availability of NID water is due to a
substantial number of other present users not presently using their full
contract allotments, not a reliable basis for predicting future water
availability to Teichert." As Teichert points out, this was factual error. There
are, in fact, multiple sources of water available to the property: (1) NID
provides water [***30] to
customers within its service area during the dry season, generally [**812] mid-April to mid-October. n2 Customers within
the district are entitled to a pro rata share of NID water. Teichert's pro rata
share of NID water is approximately 2,437 acre-feet per year. This is a matter
of right and has priority over anyone but other NID customers with a pro rata
allotment. Thus, so long as NID has sufficient water to meet the demand of customers
with pro rata rights, Teichert is entitled to 2,437 acre-feet per year. n2 NID
operates storage reservoirs in the Sierra Nevada and uses water from the
reservoirs to supply customers in the Coon Creek watershed. NID can augment its
supplies with supplemental water purchased from Pacific Gas and Electric
Company. [*907]
(2) NID
has surplus water available for sale. Surplus water is available because many
customers within the service area do not use their full pro rata share. Surplus
water may be purchased on a year-to-year contract basis by customers within or
without the service area. [***31] Surplus water sales are subject to the
priorities of customers with pro rata rights to NID water. Thus, if more
customers began using their full pro rata share, surplus water sales would
abate in favor of customers with pro rata rights. This is regarded as unlikely,
since the physical conditions of many properties in the area preclude
activities that would demand the owner's full pro rata share. In times of
drought, surplus water sales would abate in favor of customers with pro rata
rights. (3) NID
uses Coon Creek to deliver water to its customers. Coon Creek is a natural
watercourse. During the dry season, when NID is delivering water, most of the
flow of Coon Creek is NID water. NID water cannot be diverted for riparian and
appropriative uses. During the wet season the flows of Coon Creek are mostly
natural water flows. Teichert has both riparian and appropriative rights to use
the natural flows of Coon Creek. (4) There
is groundwater beneath the surface of the property. Teichert has the right to
use groundwater from beneath the property. It intends to use one well to
provide 1.5 acre-feet of potable water per year for its mining and processing
operations. The mining operation [***32]
will require that the mining site be dewatered, that is, groundwater
will be pumped from the mining site to enable dry mining to be performed.
Dewatering will extract 515 acre-feet of groundwater per year during the first
25 years, and then 700 acre-feet annually for the next 15 years. In addition to
the 1.5 acre-feet per year of potable water, the mining and processing
operations will require only 209 acre-feet of water. Accordingly, the
dewatering activities will produce substantially more acre-feet of water per
year than the mining and reclamation activities, but it is anticipated that
most of it will be discharged into Coon Creek or Doty Ravine. (5) The
property receives average annual precipitation of 23 inches per year. Natural
precipitation rather than irrigation will be relied upon for much of the
reclamation and agricultural uses of the property. It is
apparent the trial court believed that Teichert's right to purchase 2,437
acre-feet of water per year was on a contract basis for surplus water. That was
clearly a substantial basis for the court's conclusion that the EIR did not
sufficiently identify a source of water for the project's needs. However, that
was factual error. As noted [***33]
above, the right to 2,437 acre-feet of NID water is Teichert's pro rata
share of NID water and is a matter of right so long as NID has water to fulfill
the needs of its pro rata customers. That right has priority over the sale of
surplus water by contract and is a far more reliable [**813]
basis for predicting water availability than a contract for the purchase
of surplus water. [*908] It was
estimated that in preproject condition there were approximately 717 acres of
irrigated land in the mining area. On average that land required 2,523
acre-feet of water per year. Prior owners of the Hoffman Ranch and Coon Creek
Cattle Company irrigated 975 acres of land within the project area. Between
1992 and 1996, the average annual purchase of NID water for those properties
was 2,677 acre-feet of water. It was calculated that following reclamation, the
demand for irrigation would decrease by 314 acre-feet per year. Whether
compared to the average irrigation applied to the mining areas, or to the
average purchases of water by the Hoffman Ranch and Coon Creek Cattle Company,
a reduction of 314 acre-feet per year would place irrigation demand below
Teichert's pro rata share of NID water. Water
budgets were [***34] prepared for
preproject and postproject conditions. The water budgets identified inflow from
all sources and outflow from all sources. At the time these budgets were
prepared, the reclamation plan called for the development of three lakes
totaling 520 acres. The approved reclamation plan calls for two lakes totaling
345 acres. Under their worst case scenario, the water budgets demonstrate that
in an average year there will be ample water for the property in its
postproject condition. n3 n3
Evaporation from the lakes will result in the consumptive use of groundwater.
This will not require the use of water from NID or other surface sources, but
will draw water from the groundwater basin. Studies indicated that the
groundwater draw would not adversely affect existing groundwater users, but has
the potential to constrain or add to the cost of future development in areas
near the project site. For this reason, the effect was conservatively
classified as significant but unavoidable. During
the mining and reclamation [***35]
portions of the project portions of the property undergoing mining will
be withdrawn from agricultural use. This will result in a decrease in
irrigation water applied to the property from preproject conditions. It was
determined, through communication with NID, that NID has water supply available
to meet all water demands for the project. NID would not be required to
construct new diversions, other facilities, or seek to obtain additional
appropriative water rights. In light
of these factors, the EIR sufficiently demonstrates sources of water for
project and postproject needs. In fact, the trial court accepted that NID
currently has sufficient water supply for all project needs. However, the EIR
notes that NID cannot guarantee that it will always have sufficient water
supplies to meet the demands of its customers. The trial court noted this fact
in conjunction with its erroneous belief that Teichert's right to NID water was
on a defeasible contract basis in finding the EIR insufficient. (6) Teichert asserts, and WPCARE
concedes, that to be sufficient, an EIR need not identify a guaranteed source
of water. We agree. No water supplier [*909] can guarantee an adequate supply of water in
all [***36] circumstances. (See Sierra
Club v. West Side Irrigation Dist. (2005) 128 Cal.App.4th 690, 703 [27 Cal.
Rptr. 3d 223].) If an EIR were required to identify a guaranteed source of
water, then no EIR would ever be sufficient. The EIR identifies existing,
available, and sufficient sources of water for the project and in that respect
is sufficient. The trial
court also noted that water deliveries by NID could be cut back in drought
conditions. If NID water supplies decreased during a drought the first
cutbacks [**814] would occur in the sale of surplus water
pursuant to contracts, since customers with pro rata rights have priority to NID
water. If water supplies decreased to the point that NID could not supply the
needs of its pro rata customers, then it would cut back deliveries on an
individual basis depending on beneficial use. Uses such as orchards, golf
courses and intensive agricultural uses would have a higher priority while
gravel mining would have a lower priority. n4 The EIR notes that if water
deliveries were curtailed in the event of a severe drought, such that plants
die and lake levels fall, when water again becomes available Teichert will be
required to comply with all mitigation measures, [***37] including remediation. n4
Teichert's mining and processing activity will consume only a small fraction of
the water used on the property, and the dewatering extraction of ground water
is sufficient for that purpose. Most of the water Teichert will obtain from NID
will be used for agricultural purposes and would not share the low priority of
its mining operations. An EIR
should compare the effects of a project with the actual conditions that exist
in the area. (Environmental Planning & Information Council v. County of
El Dorado (1982) 131 Cal. App. 3d 350, 354 [182 Cal. Rptr. 317].) The
possibility of a drought is the status quo. The land is now used for
agricultural purposes. Teichert's extraction of groundwater is more than
sufficient to support its mining operations and most of the water obtained from
NID is to be used for agricultural purposes. If, as the result of a drought,
NID cannot deliver sufficient water, the land will suffer. That will happen
with or without the project. Absent a sufficient [***38] basis in the record to establish that the
project would cause a drought, exacerbate the severity of a drought, or
exacerbate the environmental consequences of a drought, and we find none, then
the EIR's discussion of the possibility of a drought is sufficient. This case
is inapposite to the authorities relied upon by WPCARE. For example, in Stanislaus
Natural Heritage Project v. County of Stanislaus (1996) 48 Cal.App.4th 182 [55
Cal. Rptr. 2d 625], the county approved a project for a large destination
resort. The EIR for the project identified a source of water for the first
phase but did not identify water sources for any other phases. Obtaining a new
source of water for a project can have [*910] significant impacts outside the project area.
For example, if a project obtained a right to divert water from a stream, the
diversion can affect fish and wildlife, riparian habitats, and other users. The
Court of Appeal concluded that while an EIR need not find a source of water, it
must address the impact of supplying water to the project. (Id. at p. 205.)
That decision hinged on the need to obtain new sources of water for the project
area. In contrast, this case does not involve a [***39] need to obtain a new source of water.
Teichert has identified existing and available sources of water that are
sufficient to meet the project needs. In Santa
Clarita Organization for Planning the Environment v. County of Los Angeles
(2003) 106 Cal.App.4th 715 [131 Cal. Rptr. 2d 186], the county approved a
residential and commercial project. The EIR for the project noted the need for
water supplies and indicated water would be obtained from water supplies of the
State Water Project (SWP). In its calculations, the EIR utilized water volumes
the SWP was originally intended to deliver. However, the SWP had never been
completed and there was a vast gap between the original intent and the actual
water supplies available. The Court of Appeal found the EIR inadequate because
"[t]he dream of water entitlements from the incomplete [**815] [SWP] is no substitute for the reality of
actual water the SWP can deliver." (Id. at pp. 717-718.) In
contrast, in this case Teichert has identified existing and available actual
sources of water. In Friends
of the Eel River v. Sonoma County Water Agency (2003) 108 Cal.App.4th 859 [134
Cal. Rptr. 2d 322], a water agency intended to significantly increase its [***40] diversion of water from the Russian River. At
the same time there were proceedings before the Federal Energy Regulatory
Commission (FERC) which could result in significant reductions of water
discharged from the Eel River into the Russian River. Although the water agency
was aware of the FERC proceedings, and even actively participated in those
proceedings, the EIR for the diversion of water from the Russian River made no
attempt to analyze the cumulative effects of both increased diversions and
decreased discharges from the Eel River. Obviously this was insufficient and
the court so held. (Id. at pp. 871-872.) In contrast, here there are no
anticipated changes in the water supply sources identified in the EIR. For these
reasons, we conclude the EIR is adequate in its identification of water
supplies available for project purposes. We conclude the record contains
sufficient evidence to support the County's findings. [*911]
DISPOSITION The
judgment is reversed. Costs on appeal are awarded to defendants and real party
in interest. (Cal. Rules of Court, rule 27(a).) Scotland,
P. J., and Butz, J., concurred. Document URL: http://ceres.ca.gov/html_lib/footers/foot98.html Copyright © 1998-2003 California Resources Agency. All rights reserved. |