116 Cal.Rptr.2d 54
Cal.App. 2 Dist.,2002.
Jan. 10, 2002.
Court of Appeal,
Second District, Division 4, California.
FRIENDS OF THE SANTA
CLARA RIVER, Plaintiff and Appellant,
v.
CASTAIC LAKE WATER
AGENCY, Defendant and Respondent.
No. B145283.
Jan. 10, 2002.
Brandt-Hawley & Zoia and Susan Brandt-Hawley,
for Plaintiff and Appellant.
Robert H. Clark, General Counsel, Castaic Lake Water Agency, and Kane, Ballmer
& Berkman and R. Bruce Tepper, Jr., for Defendant and Respondent.
CHARLES S. VOGEL, P.J.
INTRODUCTION
In 1995, the California State Department of Water
Resources (DWR) and water contractors of the State Water Project (SWP) reached
an historic agreement, known as the Monterey Agreement, changing the
allocations between agricultural and urban contractors of entitlements to SWP
water. A major component of the Monterey Agreement was the transfer of
entitlements up to 130,000 acre feet per year from agricultural contractors to
urban contractors, on a willing buyer-willing seller basis. Pursuant to the
Monterey Agreement, respondent Castaic Lake Water Agency (respondent) purchased
from the Kern County Water Agency (KCWA) and its member district the Wheeler
Ridge-Maricopa Water Storage District (WRMWSD) entitlement to 41,000 acre feet
per year of SWP water.
Respondent approved this transfer after certifying a project environmental
impact report (EIR) pursuant to the California Environmental Quality Act
(CEQA), Public Resources Code section 21000 et seq. [FN1] In the present case
appellant Friends of the Santa Clara River (appellant), a nonprofit California
corporation, challenges the sufficiency of respondent's EIR.
FN1. All further statutory
references are to the Public Resources Code unless otherwise indicated. A1l
references to "Guidelines" are to the CEQA regulations in Title 14,
California Code of Regulations.
Previously, the Central Coast Water Authority (CCWA) as lead agency prepared an
EIR on the environmental effects statewide of implementing the Monterey
Agreement (the Monterey Agreement EIR). Then the Belridge Water Storage
District, one of the member districts of KCWA, as lead agency prepared an EIR
on the environmental effects in Kern County of selling up to 130,000 acre feet
of SWP entitlements to then unidentified purchasers (the Belridge EIR). Then
respondent's EIR "tiered" on the Monterey Agreement EIR and the
Belridge EIR.
Appellant unsuccessfully petitioned the trial court in the present case for a
writ of mandate compelling respondent to set aside the certification of
respondent's EIR and approval of this project, on various grounds of alleged
failure to comply with CEQA. Appellant appealed the judgment denying its
petition for a writ of mandate.
While the present appeal was pending, the Court of Appeal for the Third
Appellate District found the Monterey Agreement EIR inadequate and ordered it
decertified. (Planning & Conservation League v. Department of Water
Resources (2000) 83 Cal.App.4th 892, 100 Cal.Rptr.2d 173, review denied
Dec. 13, 2000, hereafter cited as PCL.) We conclude this requires decertifying
respondent's tiered EIR.
FACTUAL
AND PROCEDURAL BACKGROUND
The
Monterey Agreement
The SWP was constructed in the 1960's. It is a
complex system of reservoirs, dams, power plants, pumping plants, canals, and
aqueducts for storage and delivery of water. DWR manages the SWP. DWR has
contracts with water contractors to deliver water to the contractors. Each such
contract sets forth a maximum annual entitlement. DWR has historically
delivered less water than the entitlements. The reliability of delivery is
approximately 50 percent of entitlements.
Before the Monterey Agreement, shortfalls in deliveries due to prolonged
droughts and other factors led to friction among the contractors over obtaining
the available SWP water. Urban and agricultural contractors each believed the
other was receiving preferential treatment. This friction was exacerbated by a
provision in the SWP contracts that in years when shortfalls occurred,
agricultural contractors were required to incur the first delivery cutbacks. [FN2]
Because contractors pay certain fixed costs to finance the SWP regardless of
actual deliveries, agricultural contractors suffered severe delivery reductions
with little relief from their financial obligations. Litigation was threatened.
DWR, agricultural and urban water contractors met and negotiated the Monterey
Agreement to avoid litigation and to increase the reliability of supply to all
contractors. (PCL, supra, 83 Cal.App.4th at pp. 901-902, 100 Cal.Rptr.2d
173.)
FN2. Under article 18(a) of
then existing contracts, deliveries to agricultural contractors were reduced by
50 percent in any one year or a total of 100 percent in seven consecutive
years, before deliveries were reduced to other contractors. (PCL, supra,
83 Cal.App.4th at p. 899, 100 Cal.Rptr.2d 173.)
Under the Monterey Agreement, all future allocations of SWP water are based on
entitlements; when supply is insufficient to meet requests, deliveries to all
contractors will be reduced in proportion to their entitlements; no longer will
agricultural contractors be required to absorb the first reductions. This
increases the reliability of supply to agricultural contractors.
Inferably in return, under the Monterey Agreement, agricultural contractors
"will make available for permanent transfer to Urban Contractors on a
willing buyer-willing seller basis 130,000 acre-feet of annual entitlements,
with [KCWA] being responsible for any portion of this amount not made available
by other Ag Contractors." This will allow urban contractors to obtain additional
entitlements, thereby slightly increasing their overall deliveries even in
times of shortage.
In addition, the Kern Fan Element, a property acquired by DWR for water
banking, will be transferred to agricultural contractors, 45,000 acre feet of
agricultural contractors' entitlements will be retired, and various operational
changes will be made to improve efficiency and flexibility of the system.
The
Monterey Agreement EIR
The parties to the Monterey
Agreement determined that its implementation could have potential environmental
consequences and therefore an EIR was required. They designated CCWA, one of
the SWP contractors, as lead agency to prepare the Monterey Agreement EIR. CCWA
prepared the draft and final EIR's on implementation of the Monterey Agreement
in May and October 1995.
The introduction to the draft Monterey Agreement EIR stated it is a
"program" EIR. Reiterating the criteria for a program EIR found in
Guideline 15168, it stated: "The purpose of a Program EIR is to document a
series of actions so related that they can be characterized as one project. The
actions may be related in one or more of the following ways: by geographical
proximity; as logical parts in a chain of contemplated actions; in connection
with the issuance of rules, regulations, plans, or **57 other general criteria to govern the
conduct of a continuing program; or as individual activities carried out under
the same authorizing statutory or regulatory authority and having generally
similar environmental effects that can be mitigated in similar ways. The
proposal to implement the Monterey Agreement fulfills both the second and third
criteria above, i.e., logical parts in a chain of contemplated actions, and a
series of actions related to the issuance of rules, regulations, plans, and
other general criteria to govern the conduct of a continuing program."
Again reiterating matter in Guideline 15168, it stated the advantages of a
program EIR are that it may: "provide an occasion for a more exhaustive
consideration of effects and alternatives than would be practical in an EIR on
an individual action; ensure consideration of cumulative actions that might be
slighted in a case-by-case analysis; avoid duplicative reconsideration of basic
policy considerations; allow the Lead Agency to consider broad policy
alternatives and program-wide mitigation measures at an early time when the
agency has greater flexibility to deal with basic problems or cumulative
impacts; and allow reduction in paperwork."
The Monterey Agreement EIR identified five major components of the Monterey
Agreement with potential environmental effects: (1) revision of the methodology
used to allocate water among contractors, (2) retirement of 45,000 acre feet of
agricultural entitlement, (3) transfer by sale between willing sellers and
willing buyers of 130,000 acre feet of entitlements from agricultural to urban
contractors, (4) changes in the Kern Fan Element of the Kern Water Bank, and
(5) changes in the manner Castaic Lake and Lake Perris terminal reservoirs may
be operated. In general, the Monterey Agreement EIR determined the
environmental effects that were capable of quantification at that time were
negligible.
With regard to the change in the method of allocating entitlements, it
summarized, "Changes in the method of allocating water become relevant
only in years when demand exceeds available supply. During such years,
following enactment of the principles contained in the Monterey Agreement,
shortages will be shared proportionately by all contractors rather than be borne
primarily by Agricultural Contractors as is the current practice. Thus, during
future deficit years Agricultural Contractors can anticipate larger deliveries
of water and Urban Contractors can expect smaller quantities of water than
would have been the case in the past. These changes bring about a decrease in
the variability of supplies delivered to Agricultural Contractors while
increasing slightly that for the Urban Contractors. [¶] Added reliability of
deliveries to Agricultural Contractors could increase the continuity of
agricultural activities in these service areas. Added variability of water
deliveries to Urban Contractors can, however, be offset by their acquisition of
additional entitlement offered for sale by Agricultural Contractors as outlined
below, and through other measures included in the program for increased water
management flexibility."
With regard to the transfers of entitlements, it summarized: "The transfer
of 130,000 AF of water entitlement from Agricultural Contractors to Urban Contractors
and non-SWP Contractors has the potential to affect activities and land use
patterns in those jurisdictions both relinquishing and acquiring the
entitlement. Effects in those areas relinquishing water entitlement are likely
to be centered on agricultural practices while those in areas acquiring water
entitlement may relate to growth accommodation. The location of the eventual
sellers and buyers of water entitlements is not known at this time."
"SWP operations would not be adversely affected by the shift in deliveries
among Contractors."
Belridge
EIR
In contemplation of the transfer
of up to 130,000 acre feet of SWP entitlements from KCWA pursuant to the
Monterey Agreement, the Belridge Water Storage District as lead agency prepared
a draft and final EIR in April and June of 1998 evaluating the effects in Kern
County of such transfers. It evaluated the effects on the Belridge Water
Storage District, the Lost Hills Water District, and the WRMWSD (all member
districts of KCWA) of their transfer of SWP entitlements to yet undetermined
purchasers.
The Belridge EIR repeatedly described the project being studied as a transfer
of up to 130,000 acre feet of entitlements under the Monterey Agreement.
It stated: "The entitlement transfer would occur under the Monterey
Agreement.... The benefits and impacts of the Monterey Agreement were evaluated
in a separate environmental impact report [the Monterey Agreement EIR] which is
discussed below and incorporated into this report by reference. However, to
understand the potential benefits and impacts of the entitlement transfer,
conditions that existed prior to the Monterey Agreement and after the Monterey
Agreement are discussed."
The Belridge EIR then summarized how deliveries of SWP water differ before and
after the Monterey Agreement. It also summarized in detail the Monterey
Agreement EIR, which it incorporated by reference.
The Belridge EIR repeatedly stressed that under the changes made by the
Monterey Agreement in allocating water during periods of shortage, agricultural
contractors would not disproportionately suffer reduced deliveries, and
therefore would enjoy increased reliability of deliveries even in times of
shortage.
These assumptions enabled the Belridge EIR to conclude that the transfer of up
to 130,000 acre feet of entitlements from the member districts would not
adversely affect at all the irrigated agricultural lands therein, because
relinquishment of the entitlements would be compensated, on an average annual
basis, by the increased reliability of SWP deliveries pursuant to the Monterey
Agreement.
Respondent's
EIR
The EIR in dispute in the present
case is the EIR prepared by respondent in February 1999 on the proposed
transfer to respondent of 41,000 acre feet per year of SWP entitlement from
KCWA and its member district WRMWSD.
The introduction section of respondent's EIR expressly stated, "This
EIR is a Project EIR that tiers from " (1) a prior 1988 EIR by
respondent, "Capital Program and Water Plan Including Acquisition of
Supplemental Water and of a Proposed Second Plant Site", (2) the Monterey
Agreement EIR, and (3) the Belridge EIR. It stated the proposed transfer
"is an example of the individual projects envisioned in the Monterey
Agreement and evaluated on a programmatic basis in the Monterey Agreement
EIR."
This introduction stated that "As a result of the recently adopted
Monterey Agreement, [respondent] has the opportunity to purchase additional SWP
entitlement beyond its current entitlement. The opportunity to acquire
additional entitlement under the terms of the Monterey Agreement disappears
when the subject entitlement (130,000 AFY) is transferred to [respondent] or
other entities. A summary of the Monterey Agreement is presented below, and a
more complete discussion of the SWP is included in the Monterey Agreement
FEIR." A separate section of the introduction described "the Monterey
Agreement/Amendment and its anticipated effect on historic water
deliveries." After summarizing the major provisions of the Monterey
Agreement, it concluded, "The Monterey Agreement has three primary
objectives: (1) to increase the reliability of all SWP Contractors' water
supplies; (2) to stabilize the rate structure to improve the financial
viability of the SWP; and (3) to increase water management flexibility for all
SWP Contractors. A permanent transfer of agricultural entitlement to an area
with urban development potential such as that analyzed in this document is one
of the ways that these objectives are intended to be met."
Respondent's EIR also discussed the Belridge EIR. It stated, "An
independent EIR evaluating the environmental impacts of the sale of SWP
entitlement within Kern County was completed by Belridge Water Storage District
in June 1998. Issues identified in that EIR are not evaluated further in this
EIR. Appropriate sections of the Belridge EIR ... are incorporated
herein." It added that the proposed transfer would not significantly
decrease water deliveries or irrigated acreage within KCWA or WRMWSD because,
with implementation of the Monterey Agreement, "SWP deliveries to
agricultural users will not be subject to absorbing the initial deficiencies
during droughts and other unreliable delivery scenarios." The project
description section acknowledged that this proposed transfer, "assuming it
proceeds under the Monterey Agreement, will fulfill part of [KCWA's] commitment
[under the Monterey Agreement to transfer up to 130,000 acre feet of
entitlements to urban contractors]."
A commenter on respondent's draft EIR, Santa Clarita Organization for Planning
the Environment (SCOPE), commented that the draft EIR was deficient in failing
to analyze impacts on land in Kern County or on Castaic Lake as a terminal
reservoir of the SWP. Respondent responded that those impacts had already been
evaluated in the Belridge EIR and the Monterey Agreement EIR and therefore were
not required to be addressed in respondent's EIR.
Despite these numerous references relying on the Monterey Agreement and the
Monterey Agreement EIR, respondent's EIR also asserted the proposed transfer of
SWP entitlements could take place without the Monterey Agreement, under pre-
Monterey Agreement contract law, with the consent of all parties and DWR. It
acknowledged that the Monterey Agreement EIR was challenged in the PCL
case, had been upheld by the Sacramento Superior Court, but was still
challenged in the appeal then pending.
A comment from the Environmental Defense Center on the proposed final EIR
complained that the EIR expressly tiers on the Monterey Agreement EIR, the
status of which was questionable because it was in litigation in the Court of
Appeal for the Third Appellate District; it also asserted the Belridge EIR was
inappropriate for tiering. Respondent's consultant replied, "The proposed
FEIR identifies that the proposed project may proceed either under the
provisions of the Monterey Agreement or under the terms of the Kern County
Water Agency Contract before it was modified by the Monterey Amendment.... The
proposed final EIR identified the referenced litigation and Superior Court
ruling.... [¶] The EIR does not tier from the Belridge ... EIR but incorporates
appropriate sections by reference.... The inclusion of the reference to the
Belridge 1998 EIR [as having been tiered on, as distinguished from having been
incorporated by reference] is an error."
On the present appeal respondent admits that its EIR tiers on the Monterey
Agreement EIR. Respondent states its EIR incorporates by reference the Belridge
EIR.
Trial
Proceedings in the Present Case
Appellant Friends of Santa Clara
River filed a petition for a writ of mandate compelling respondent to set aside
respondent's certification of its EIR and approval of the project, primarily on
the ground respondent failed to comply with CEQA. Appellant alleged various
defects in the EIR and respondent's findings. The alleged defects did not
involve the Monterey Agreement EIR or the then pending PCL appeal. The
trial court denied appellant's petition, finding that the EIR was adequate and
that appellant's other contentions lacked merit. Appellant appealed from the
judgment denying the petition.
The
PCL Case
In September 2000, after the
trial court's judgment in the present case, the Court of Appeal for the Third
Appellate District held the Monterey Agreement EIR prepared by CCWA was
inadequate. (PCL, supra, 83 Cal.App.4th 892, 100 Cal.Rptr.2d 173.) The
Court of Appeal found two major defects. (1) The state DWR, not CCWA, should
have prepared the report as the lead agency; DWR has a statewide perspective
and expertise on how allocation of water to another part of the state has
implications for distribution throughout the system. (83 Cal.App.4th at pp.
903-907, 100 Cal.Rptr.2d 173.)(2) The EIR did not adequately address the
alternative of "no project"; it should have addressed the environmental
implications of invoking article 18(b) of existing contracts, under which
entitlements would be permanently reduced to reflect actual delivery patterns.
(83 Cal.App.4th at pp. 908-920, 100 Cal.Rptr.2d 173.) The court commented,
"Perhaps the deficiencies in the EIR relate to the provincial experience
of the lead agency, a topic we addressed earlier. We conclude the EIR failed to
meet the most important purpose of CEQA, to fully inform the decision makers
and the public of the environmental impacts of the choices before them. A new
EIR must, therefore, be drafted. [¶] In view of our earlier conclusion that DWR
must serve as lead agency under CEQA, we need not, as we ordinarily would,
address the other alleged deficiencies in this EIR. (Pub. Resources Code, § 21005,
subd. (c).) We need not hypothesize on the remaining issues because DWR, with
its expertise on the statewide impacts of water transfers, may choose to
address those issues in a completely different and more comprehensive
manner." (83 Cal.App.4th at p. 920, 100 Cal.Rptr.2d 173.)
The Court of Appeal reversed the judgment of the Sacramento Superior Court and
remanded with directions to "issue a writ of mandate vacating the
certification of the EIR," to "consider such orders it deems
appropriate under Public Resources Code section 21168.9, subdivision (a)"
and to "retain jurisdiction over this action until DWR certifies an EIR in
accordance with CEQA standards and procedures that meets the substantive
requirements of CEQA." (83 Cal.App.4th at p. 926, 100 Cal.Rptr.2d 173.) It
noted, "We earlier declined to stay implementation of the Monterey
amendments and transfer of the Kern Fan Element. Consequently, the project was
permitted to proceed pending disposition of this appeal. The record does not
reflect the current status of the project and, in the absence of such
information, we shall issue no orders concerning further implementation of the
project. The trial court, acting under the authority provided by Public
Resources Code section 21168.9, is the more appropriate forum to consider and
rule upon requests to enjoin all or portions of the project pending completion
of administrative and judicial proceedings necessitated by our opinion." (Id.,
fn. 16, 100 Cal.Rptr.2d 173.)
Expanded
Issue on This Appeal
In its appellant's opening brief
on the present appeal, appellant reasserted various arguments that appellant
had unsuccessfully raised below concerning respondent's EIR and findings.
Appellant's opening brief added, cursorily, that the decision in the PCL
appeal, during pendency of this appeal, "completely shattered"
respondent's EIR that was tiered on the EIR decertified in the PCL
decision. Appellant more fully developed this argument in its appellant's reply
brief. We requested and received supplemental briefs from the parties on this
issue.
LEGAL
BACKGROUND: TIERING OF EIR'S
Tiering "means the coverage
of general matters and environmental effects in an environmental impact report
prepared for a policy, plan, program or ordinance followed by narrower or
site-specific environmental impact reports which incorporate by reference the
discussion in any prior environmental impact report and which concentrate on
the environmental effects which (a) are capable of being mitigated, or (b) were
not analyzed as significant effects on the environment in the prior
environmental impact report." (§ 21068.5; Guidelines 15152, 15385.)
Tiering is favored by the Legislature to streamline the regulatory process and
avoid wasteful duplication of effort. (Stanislaus Natural Heritage Project
v. County of Stanislaus (1996) 48 Cal.App.4th 182, 197-198, 55 Cal.Rptr.2d
625; §§ 21093, 21094; Guideline 15152(b).) "To achieve this purpose,
environmental impact reports shall be tiered whenever feasible, as determined
by the lead agency." (§ 21093, subd. (b).) "Where a prior
environmental impact report has been prepared and certified for a
program, plan, policy, or ordinance, the lead agency for a later project that
meets the requirements of this section shall examine significant effects of the
later project upon the environment by using a tiered environmental impact
report ...." (§ 21094, subd. (a), italics added.) "All public
agencies which propose to carry out or approve the later project may utilize
the prior environmental impact report and the environmental impact report on
the later project to fulfill the requirements of Section 21081 [which concerns
findings necessary in order to approve a project if significant environmental
effects have been identified]. When tiering is used pursuant to this section,
an environmental impact report prepared for a later project shall refer to the
prior environmental impact report and state where a copy of the prior
environmental impact report may be examined." (§ 21094, subds.(d), (e).)
"The later EIR ... should state that the lead agency is using the tiering
concept and that it is being tiered with the earlier EIR." (Guideline
15152(g).)
DISCUSSION
Respondent's EIR expressly tiered on the Monterey
Agreement EIR. Section 21094, subdivision (a) authorizes tiering where the
previous EIR was certified. As a result of the PCL decision, the
Monterey Agreement EIR is no longer certified. Respondent's EIR therefore has a
defect. The question presented for us is whether that error was prejudicial. (§
21005, subd. (b).)
Respondent contends that although its EIR tiered on the Monterey Agreement EIR,
it did not expressly or specifically incorporate any substantive analysis from
specific portions of the Monterey Agreement EIR. But respondent's reliance on
the Monterey Agreement EIR is implicit in the concept of tiering, even without
express reference to portions of the prior EIR's analysis. The express
statement that respondent's EIR tiers on the prior EIR may be treated as an
admission that respondent relied upon and needed to rely upon the Monterey
Agreement EIR. (Guideline 15152(g).)
Aside from a few cursory statements that the present transfer could legally be
accomplished under pre-Monterey Agreement contracts, a point we discuss later,
respondent's EIR repeatedly referenced this project's part of the overall
scheme envisioned by the Monterey Agreement. It stated this EIR was a project
EIR tiered on the Monterey Agreement EIR, and that the project may be viewed as
one of the projects "evaluated on a programmatic basis in the Monterey
Agreement EIR."
Respondent's EIR also expressly tiered on, or at least expressly incorporated
and relied upon, the analysis in the Belridge EIR. Respondent's EIR
acknowledged that the transfer would not affect irrigated lands in Kern County
because of the increased reliability of deliveries to agricultural contractors
under the Monterey Agreement, and that the present transfer would fulfill part
of KCWA's commitment in the Monterey Agreement. The Belridge EIR, on which
respondent relied, repeatedly stated that the potential transfers of up to
130,000 acre feet would be made pursuant to the Monterey Agreement and would
have no significant effect on the irrigated lands, due to the increased
reliability of deliveries under the Monterey Agreement. Respondent's reliance
on the Belridge EIR illustrates respondent's implied acknowledgement that the
transfer in this case is part of an overall larger scheme, analyzed on a
programmatic basis in the Monterey Agreement EIR. The PCL decision also
emphasizes the importance of the statewide perspective in analyzing the
implications of water entitlement transfers for the state and SWP as a whole.
We therefore find unpersuasive respondent's present argument that respondent
did not rely on the Monterey Agreement EIR.
At oral argument respondent offered a variant of this contention. According to
respondent: "the project" being analyzed in respondent's EIR was only
the transfer of 41,000 acre feet of entitlements from WRMWSD to respondent;
respondent was only required, therefore, to analyze the environmental effects
of that narrow project; respondent adequately evaluated the local environmental
effects of the subject transfer; respondent was not required to analyze
the effects of the transfer on irrigated lands in Kern County or on the SWP
upstream from Kern County, and to any extent respondent relied on the Belridge
EIR and Monterey Agreement EIR to do so, this was surplusage; therefore the
tiering on the Monterey Agreement EIR was harmless and does not require setting
aside respondent's EIR that was otherwise adequate, viewed as a stand-alone
document evaluating the local environmental impacts of this specific project.
Appellant answers that respondent was required to review "the whole of the
project." (Guideline 15378(a) [" 'Project' means the whole of an
action"].)
Respondent's argument is not persuasive. The purpose of an EIR is to inform the
public and the decision makers of the environmental effects of a project.
Implicit in respondent's argument is an innuendo the public and decision makers
in respondent's service area do not care about the upstream effects of this
project. But in any event, this case does not squarely present that issue. This
is not a case where (1) respondent neglectfully failed or deliberately refused
to evaluate "upstream" environmental effects and (2) appellant
challenged such an EIR as inadequate based on its failure to review upstream
effects. Rather, respondent's EIR assumed the public and decision makers would
want to know (1) that this project implements the Monterey Agreement, the
environmental effects of which were analyzed in the Monterey Agreement EIR and
found to be negligible, and (2) that the environmental effects in Kern County
were studied in the Belridge EIR and found to be insignificant because of the
increased reliability of water deliveries to agricultural contractors under the
Monterey Agreement. The PCL decision undermined those premises by
decertifying the Monterey Agreement EIR.
Respondent next contends the tiering on the Monterey Agreement EIR was not
crucial because respondent and KCWA could legally have accomplished the
transfer of entitlements under SWP contract law existing prior to the Monterey
Agreement. Respondent cites the following portions of its EIR: section 1.3 of
the introduction stated, "The SWP entitlement transfer analyzed in this
document may proceed either under the provisions of the Monterey Amendment
[FN3] to KCWA water supply agreement with the DWR (Contract), or under the
provisions of KCWA's Contract before it was modified by the Monterey
Amendment," and again, "The entitlement transfer that is the subject
of this EIR is of the type that falls within the provisions of the Monterey
Amendment. However, this water transfer could occur without the Monterey
Amendment with the consent of all affected parties." The project
description section included, "This water transfer is expected to be
subject to the conditions of the Monterey Amendment, but is not necessarily
dependent upon the Monterey Amendment. With the cooperation of the
participating agencies and the California Department of Water Resources (DWR),
the transfer could occur in the absence of the Monterey Amendment."
Finally, in response to comments from the Environmental Defense Center that
tiering on the Monterey Agreement EIR was questionable in light of the PCL
litigation, respondent's consultant stated, "The proposed FEIR identifies
that the proposed project may proceed either under the provisions of the
Monterey Agreement or under the terms of the Kern County Water Agency Contract
before it was modified by the Monterey Amendment."
FN3. By the Monterey
"Amendment" respondent's EIR meant amendment of the SWP contracts
between DWR and the approving contractors, to implement the principles of the
Monterey Agreement.
These assertions are based on article 41, a standard provision of state water
contracts, stating that "No assignment or transfer of this contract or any
part hereof, rights hereunder, or interest herein by the Agency shall be valid
unless and until it is approved by the State and made subject to such
reasonable terms and conditions as the State may impose."
Respondent's argument is based on a straw man. The issue in this case is not
the legal authority of KCWA to sell and of respondent to buy SWP water
entitlements, but rather the adequacy of the evaluation of the environmental
effects of doing so. The Belridge EIR evaluated those effects in Kern County
pursuant to the Monterey Agreement, concluding that selling the entitlements
would not have an effect on irrigated lands because, on average, it would be
compensated by the increased reliability of deliveries to agricultural
contractors under the Monterey Agreement. Neither the Monterey Agreement EIR,
nor the Belridge EIR, nor respondent's EIR evaluated the environmental effects
on the seller's irrigated lands of selling the entitlements under pre-Monterey
Agreement conditions, with agricultural contractors subject to the first and
severest reductions in times of shortage.
Respondent contends this shortcoming is alleviated by the inclusion of
discussions in the Belridge EIR and respondent's EIR of a "no project
alternative." This is incorrect. The no project alternative in the
Belridge EIR was: not selling the entitlements. The no project alternative in respondent's
EIR was: not buying the entitlements. Neither addressed the environmental
effects of transferring the entitlements without the protections for
agricultural contractors in the Monterey Agreement.
We conclude respondent's tiering on the now decertified Monterey Agreement EIR
was prejudicial error. The judgment must be reversed because the certification
of respondent's EIR must be vacated, based on the PCL /tiering problem.
The question arises whether we should address the other alleged defects
that were litigated below and raised in appellant's opening brief. We asked the
parties to address whether these issues were moot if the judgment were reversed
based on the PCL /tiering problem. Both parties remind us of section
21005, subdivision (c), which provides, "It is further the intent of the
Legislature that any court, which finds, or, in the process of reviewing a
previous court finding, finds, that a public agency has taken an action without
compliance with this division, shall specifically address each of the alleged
grounds for noncompliance." A treatise states, "This language, which
courts may not treat as mandatory, is apparently intended to avoid situations
in which a court, presented with numerous theories as to why a respondent agency
purportedly violated CEQA, chooses to issue a writ based solely on one or a
handful of theories, leaving the parties to wonder whether or not the
unaddressed theories had merit. In such situations, where the respondent agency
must conduct a second CEQA process to cure the problems identified by the
court, the agency often does not know whether to modify its environmental
document (or findings) to address concerns raised by the petitioners but
ignored by the court." (Remy et al., Guide to the California Environmental
Quality Act (10th ed. 1999) Judicial Review, pp. 646-647.)
Section 21005, subdivision (c) thus requires only that if we find other
respects in which the EIR was defective we should describe them for the
guidance of the parties. We have examined all of appellant's other contentions
and find them to be without merit. If the PCL /tiering problem
had not arisen, we would have affirmed the judgment. Section 21005, subdivision
(c) does not require us to lengthen this opinion by addressing in detail why we
reject appellant's other contentions. Appellant's supplemental reply
brief so concedes: "The court's discussion of all aspects of CEQA
noncompliance is respectfully requested, while areas of compliance are not
required to be addressed."
This suggests that respondent may be able to cure the PCL problem by
awaiting action by the state DWR complying with the PCL decision, then
issuing a subsequent EIR, supplement to EIR, or addendum to EIR (Guidelines
15162, 15163, 15164) tiering upon a newly certified Monterey Agreement EIR.
Appellant itself so suggests.
Like the court in PCL, supra, 83 Cal.App.4th at page 926 and footnote
16, 100 Cal.Rptr.2d 173, we leave to the trial court's discretion whether to
enjoin all or portions of respondent's project pending completion of an
adequate EIR. The trial court is in a better position than this court to
determine factually the current status of the PCL litigation or of a new
Monterey Agreement EIR.
DISPOSITION
The judgment is reversed. The trial court shall
issue a writ of mandate vacating the certification of the EIR, shall retain
jurisdiction until respondent certifies an EIR complying with CEQA consistent
with the views expressed in this opinion, and shall consider such orders it
deems appropriate under section 21168.9. The parties shall bear their own costs
on appeal.
We concur: HASTINGS and CURRY, JJ.