|
![]() |
100 Cal.Rptr.2d 889, 00 Cal. Daily Op. Serv. 8762, 2000
Daily Journal D.A.R. 11,559 VEDANTA SOCIETY OF SOUTHERN CALIFORNIA, Plaintiff and
Respondent, v. CALIFORNIA QUARTET, LTD., et al., Defendants and Appellants.
NORBERTINE FATHERS OF ORANGE et al., Plaintiffs and Respondents, v. CALIFORNIA
QUARTET, LTD., et al., Defendants and Appellants. ENDANGERED HABITATS LEAGUE, INC., et al., Plaintiffs and
Respondents, v. CALIFORNIA QUARTET, LTD., et al., Defendants and Appellants. No. G026580. Court of Appeal, Fourth District, Division 3, California. Oct. 30, 2000. SUMMARY Environmental groups
and neighbors opposed to a proposed development brought declaratory relief
actions to establish that the various project approvals were based on an
erroneous certification of the environmental impact report (EIR). The actions
were consolidated, and the trial court granted summary adjudication for
plaintiffs, reasoning that the county board of supervisors did not take
appropriate action, and as a result, the EIR had never been properly
certified. In voting on whether the
unelected county planning commission properly certified the EIR, the board of
supervisors reached a two-to-two tie, after a fifth supervisor recused himself.
(Superior Court of Orange County, Nos. 791309, 804137, and 804139, Robert E.
Thomas, Judge.) The Court of Appeal
affirmed. The court held that the certification of the EIR by the unelected
county planning commission could not be upheld on appeal as a result of a tie
vote by the elected county board of supervisors. The appeal had to be decided
by a majority of the board. The ultimate responsibility for approving the EIR
was in the elected board of supervisors, not the unelected planning commission.
Cal. Code Regs., tit. 14, 15185, subd. (b), builds on the requirement of an
appellate process in Cal. Code Regs., tit. 14, 15090, subd. (b), by explicitly
obligating the elected decisionmakers to consider a certified EIR and make
findings about it under Cal. Code Regs., tit. 14, 15091 and 15093. Although the
board could have adopted findings of the planning commission, a tie vote did
not have the *518 effect of adopting the findings. The board was
required to act in a conscious, aware, and deliberative manner. The court
further held that the board of supervisor's adoption, by a three-to-one vote,
of a resolution declaring that the project did not trigger the preparation of a
subsequent EIR, and that a mere addendum would suffice for the existing EIR,
did not cure the fact that the original EIR was never validly certified.
Finally, the court held that plaintiffs were not required to seek
administrative mandamus rather than declaratory relief. (Opinion by Sills, P.
J., with Rylaarsdam and Bedsworth, JJ., concurring.) COUNSEL Latham & Watkins
and Robert K. Break for Defendant and Appellant County of Orange. Law Offices of
William D. Ross, William D. Ross and Carol B. Sherman for Defendants and
Appellants California Quartet, Ltd., Aradi, Ltd., and Aradi, Inc. Connor, Blake &
Griffin, Edmond M. Connor and David J. Hesseltine for Plaintiff and Respondent
Vedanta Society of Southern California. Jensen &
Coeur-Barron and VerLyn N. Jensen for Plaintiffs and Respondents Norbertine
Fathers of Orange and Saddleback Meadows Land Conservancy. *521 Law Offices of Mary
L. Hudson, Mary L. Hudson; Law Offices of Rachel J. Sater and Rachel J. Sater
for Plaintiffs and Respondents Endangered Habitats League, Inc., Sea and Sage
Audubon Society, Inc., and Rural Canyons Conservation Fund. SILLS, P. J. I. Introduction Tie votes mean
different things in different contexts. The fictitious spelunkers in Lon
Fuller's famous law review article, finding themselves trapped in a cave and
resorting to cannibalism to stay alive for the requisite amount of time until a
rescue party reached them, were sentenced to death for murder when the mythical
five-person Supreme Court of Newgarth, reviewing the conviction of a lower
court, tied two to two. The tie was the result of one justice on the
five-person panel dithering to the point that he was unable to resolve his own
doubts, and consequently withdrawing from the decision of the case. (See
Fuller, The Case of the Speluncean Explorers (1949) 62 Harv. L.Rev. 616, 631,
645.) Fuller's spelunkers' case demonstrated the classic common law rule that a
tie, in the context of an appeal from a lower court, leaves the decision being
appealed from intact. His Justice Tatting in effect cast a vote to affirm by
withdrawing from the case. [FN1] FN1 Indeed, Chief Justice Rehnquist recently mentioned the
spectre of an inadvertant affirmance of a lower court decision by a tie vote of
the United States Supreme Court as a factor weighing against his recusal in a
case where his son was a partner in a firm representing one of the litigants as
local counsel in Boston. In a separate statement filed in Microsoft Corporation
v. United States (Sept. 26, 2000, Nos. 00-139 and 00-261) ___ U.S. ___ [2000 WL
1052937], he wrote that if he recused himself "[n]ot only is the Court
deprived of the participation of one of its nine members, but the even number
of those remaining creates a risk of affirmance of a lower court decision by an
equally divided court." It is not quite that
way in the statutory thicket that is California's Environmental Quality Act
(Pub. Resources Code, 21000 et seq.), CEQA for short. Appeals in American
jurisprudence typically do not require the reviewing court to take evidence
anew and agree on certain written findings. By contrast, appeals within the
context of a local lead agency's decisionmaking process under CEQA do. *522 Appeals within a lead
agency under CEQA are governed both by statute (Pub. Resources Code, 21151) and
regulations promulgated by the California Resources Agency. (See Cal. Code
Regs., tit. 14, 15000.) [FN2] When an unelected planning commission
certifies an environmental impact report (or EIR), that certification may be
appealed to the relevant agency's elected decisionmaking body, if it has one.
(See Pub. Resources Code, 21151, subd. (c).) In such a case, a regulation
specifies that the "decision-making body to which an appeal has been
made" must not only "consider" the EIR, but make certain written
findings if appropriate (see 15185, subd. (b)) concerning the significant
environmental effects associated with the project (see 15091, subd. (a), 15093,
subd. (b)). Such written findings are "appropriate" in any case where
the EIR identifies significant environmental effects ( 15091, subd. (a)) or
where significant effects are identified but not "substantially lessened"
( 15093, subd. (b)). FN2 All references to any section numbered in the 15000's are
to title 14 of the California Code of Regulations, as is any reference to
"Guideline" or "Guidelines." All references to "title
14" are to the California Code of Regulations. The need for consideration,
written findings, and even a "brief explanation" (see 15091, subd.
(a)) by the body to which the appeal is taken is simply incompatible with the
approval by acquiescence. Consideration and written findings imply conscious,
affirmative action, not default adoption of the status quo by inertness. In the present case,
the county planning commission certified an EIR for a 705-unit housing
development in Trabuco Canyon. The EIR identified a variety of significant
environmental impacts, including the change of night views from unlit dark open
space to "urban night environment." A group of neighbors led by the
Vedanta Society of Southern California appealed the certification to the Orange
County Board of Supervisors. Supervisor Silva recused himself. The board held a
hearing and then deadlocked two to two on Supervisor Steiner's motion to adopt
the staff's recommendation to deny the appeal and uphold the certification. The
board's own minute order described Steiner's motion as having "failed for lack
of [a] majority." However, Supervisor Wilson then declared that the vote
upheld the planning commission's decision and the project was processed on the
assumption the EIR had been certified. In response, the
neighbors and certain environmental groups brought declaratory relief actions
to establish that the various project approvals were based on an erroneous
certification of the EIR. The actions were consolidated. In a successful
summary adjudication motion (later followed by a *523 motion for entry
of judgment), the trial court agreed with the neighbors and the environmental
groups, reasoning that the board, under the statute in the Government Code that
governs actions by county boards of supervisors (Gov. Code, 25005), had not
acted on the neighbors' appeal. Since the board had taken no action in a
context where affirmative action was required, the EIR had never been properly
certified. As one might gather from our comments
concerning CEQA's consideration and finding requirements, the trial judge's
decision was correct, though as we explain below, this result is dictated by
CEQA and its controlling regulations alone. We do not reach any issue regarding
the proper explication of Government Code section section 25005. II. Facts In 1993, California
Quartet, Ltd., purchased some 222 acres of undeveloped land in Trabuco Canyon
near St. Michael's Abbey and the Ramakrishna Monastery. In 1996, the firm
proposed a 705-unit mobilehome development on the land, for which the County of
Orange required an EIR. A draft EIR (EIR 566) [FN3] was circulated in
June 1997. FN3 Technically, a "subsequent" EIR was required
because one had been prepared in the late 1970's. Hence the record and briefing
typically refer to the EIR before us as "DS566" (for draft
subsequent) or "FS566" (for final subsequent). In late November
1997, the Orange County Board of Supervisors adopted a special set of
procedures just for the review of the circulating draft EIR. Those procedures
provided that the planning commission would determine whether to certify the
EIR in a meeting held December 3, 1997, and that any interested party could
appeal a decision by the planning commission certifying the EIR within 15 days
of the commission's decision. The appeal would be put on the agenda of a board
of supervisors' meeting within 45 days of the receipt of the appeal. The board
of supervisors would then "consider the appeal at a public meeting and
make a determination whether to uphold the appeal in whole or in part or to
deny the appeal." In the event of one of three contingencies- expiration
of the appeal period without an appeal, "denial of any appeal and
ratification of the Planning Commission's certification" or
"certification" of the EIR "by the Board of Supervisors with
modifications," it was provided that the "Building Official may issue
the grading permit." The Orange County
Planning Commission certified the final EIR 566 in December 1997. The owners of
the monastery, the Vedanta Society of *524 Southern California, timely
appealed the planning commission's certification to the Orange County Board of
Supervisors. The board held a public hearing in late February 1998 to consider
the appeal. [FN4] At the end of the hearing Supervisor Steiner
introduced a motion to deny the appeal and uphold the certification.
Reminiscent of Peter Ustinov's equivocating British diplomat, [FN5] the
vote was an opaque two to two, Supervisor Silva having recused himself. The
board's minute order stated: "Motion to deny Appeal failed for lack of
majority." However, Supervisor Wilson, acting as vice chairman of the
board, declared that the tie vote meant the planning commission's action had
been upheld. The next month the Vedanta Society filed a lawsuit (case No.
791309), seeking a declaration that the board had not made any determination of
the society's appeal, and specifically did not ratify or uphold the planning
commission's action. FN4 We grant California Quartet's request that this court take
judicial notice of a series of documents from the County of Orange Planning and
Development Services Department, showing that the public was given due notice
of the board's consideration of Vedanta's appeal. FN5 A character known for saying "his majesty's government
does not say yea, nor does it say nay, and this in no way should be construed
as an abstention." Meanwhile, California
Quartet submitted tentative tract maps for approval of a 299-unit project
involving single-family homes instead of mobilehomes. In December 1998, the
board of supervisors, this time by a vote of three to one (Supervisor Silva
still abstaining), adopted a resolution declaring that the 299-unit project did
not "trigger the preparation of a subsequent EIR" and that a mere
addendum to the already certified EIR would suffice. Two more lawsuits followed
in January 1999: The first was an ecumenical effort, in which the Norbertine
Fathers of Orange who own St. Michael's Abbey joined with the Vedanta Society
of the Ramakrishna Temple and the Saddleback Meadows Land Conservancy (case No.
804137). [FN6] The second (case No. 804139) was brought by three
environmental organizations: the Endangered Habitats League, Inc., the Sea and
Sage Audubon Society, Inc., and the Rural Canyons Conservation Fund. The three
lawsuits were consolidated in April 1999; by August, the plaintiffs in the
consolidated action brought a summary adjudication motion to establish that EIR
566 was legally inadequate under CEQA. The trial court granted the summary
adjudication motion in November, reasoning that the tie vote in February 1998 *525
was " 'no action' by the board with respect to [Vedanta's] appeal because
Government Code section 25005 required a three- member majority vote by the
Board in order for the Board to take affirmative action thereon to either deny
the Appeal or uphold it." FN6 The complaint in case No. 804137 is not your typical
dry-as-sand complaint. It begins by comparing the plaintiffs to voices "
'crying in the wilderness,' " and explicitly refers to the book of Isaiah,
the source of the phrase. (See Isaiah 40:3.) Of course, given that the
"voice in the wilderness" reference was later used to refer to
someone who, as the modern saying goes, had his head handed him on a plate (see
Matthew 3:3), it could hardly have been considered "prophetic" of the
results of the litigation, at least at the trial and, given our decision today,
the intermediate appellate level. Because this is a land use case, perhaps a
better allusion to the book of Isaiah would have been from chapter 5, verse 8:
"Woe unto them that join house to house, that lay field to field
...." (For they shall be forced to comply with CEQA.) On January 3, the
county filed a writ petition challenging the summary adjudication (case No.
G026580). However, two days later Vedanta filed a motion for entry of judgment
based on its victory in the summary adjudication. The trial court granted the
motion for entry of judgment on February 23, 2000. [FN7] The judgment
provided a declaration that EIR 566 was never validly certified; the judgment
also provided for a peremptory writ of mandate directing the county to vacate
and set aside all approvals with regard to the 299-unit project. This court
ordered that the county's writ be treated as an appeal from the judgment, and
has included California Quartet's formal appeal within the one docket number,
G026580. [FN8] FN7 Appellants raise no issue in this appeal that the summary
adjudication motion was not effectively dispositive of the litigation. FN8 Because Vedanta prevailed, the fact that it dismissed
certain claims in its complaint without prejudice does not make the judgment
any less appealable. Don Jose's Restaurant, Inc. v. Truck Ins. Exchange (1997)
53 Cal.App.4th 115 [61 Cal.Rptr.2d 370] and its progeny have no application
where the party dismissing causes of action without prejudice is the respondent
on appeal. III. Discussion A. Under CEQA and Its Regulations, an Appeal from the
Certification of an EIR by an Unelected Planning Commission Must Be Decided by
the Majority Vote of the Elected Body This case centers on
Public Resources Code section 21151, subdivision (c). [FN9] Subdivision
(c) sets forth the language governing appeals from EIR certifications made by
"a local lead agency's decisionmaking body which is not elected,"
such as the planning commission in the case before us. The language, in its
entirety, is: "When an environmental impact report is certified by a local
lead agency's decisionmaking body which is not elected, that certification may
be appealed to the agency's elected decisionmaking body, if any." FN9 All references in this opinion to "section 21151"
are to the Public Resources Code. All references to "subdivision (c)"
or to "subdivision (a)" are to section 21151. We may first dispense
with any idea that the permissive "may" in the text, or the hint
contained in the words "if any" at the tag end of the statute,
somehow allow for a situation where a county board of supervisors might have
the discretion not to provide for appeals from a planning commission *526
certification. Whatever ambiguity might be teased out of the text of section
21151 cannot withstand the plain force of state regulations, specifically
Guideline 15090, subdivision (b). Guideline 15090, subdivision (b)
unequivocally leaves no room for local agencies to omit an appeals process:
"When an EIR is certified by a non-elected decision-making body within a
local lead agency, that certification may be appealed to the local lead
agency's elected decision-making body, if one exists. For example,
certification of an EIR for a tentative subdivision map by a city's planning
commission may be appealed to the city council. Each local lead agency shall
provide for such appeals." (Italics added.) Kleist v. City of
Glendale (1976) 56 Cal.App.3d 770 [128 Cal.Rptr. 781] (Kleist) makes it clear
that Guideline 15090, subdivision (b), which requires local governments to have
an appeals procedure, is not only not beyond the purview of the enabling
statutes (see Pub. Resources Code, 21082.1, 21100 [general statutory authority
for regulations implementing CEQA]), but wholly consistent with the statutory
scheme of CEQA as a whole. In Kleist, one of the issues was whether the
Glendale City Council could delegate review and consideration of an EIR to a
special board created by city ordinance. In holding that the city council itself
was required to review and consider the EIR, the court reasoned that
"[d]elegation is inconsistent with the purpose of the review and
consideration function since it insulates the members of the council from
public awareness and possible reaction to the individual members' environmental
and economic values. Delegation is inconsistent with the purposes of the EIR
itself." (Kleist, supra, 56 Cal.App.3d at p. 779.) Applied to the present
case, it follows from the Kleist antidelegation rule that the ultimate
responsibility for approving an EIR in the case before us was in the elected
board of supervisors, not the unelected planning commission. (See Sundstrom v.
County of Mendocino (1988) 202 Cal.App.3d 296, 307 [248 Cal.Rptr. 352]
["By necessary inference, the board of supervisors cannot delegate the
responsibility" for considering an EIR "to the staff of the planning
commission"].) Now, we are not
saying (and Kleist should not be read to say) that an elected body cannot
explicitly adopt findings made by a nonelected body. In Greenebaum v. City of
Los Angeles (1984) 153 Cal.App.3d 391 [200 Cal.Rptr. 237], decided by the same
court that decided Kleist (see Greenebaum, supra, 153 Cal.App.3d at p. 403),
the Court of Appeal held that an adoption of the findings of a planning
department's deputy advisory agency by a city council was not an improper
delegation. (See id. at pp. *527 398-399, 402-403.) [FN10] But it
is also clear, from Guideline 15090, subdivision (b), that the elected decision
makers must have a real confrontation with the EIR; they cannot avoid the
required "consideration" by omitting a procedure for appeal. FN10 Greenebaum involved a 24-unit condominium project in Los
Angeles which made its way from an environmental review committee to a deputy advisory
agency to the city planning commission to the city council. Along the way, the
planning commission voted two to two, which, according to the opinion,
"left intact the action of the deputy advisory agency." (Greenebaum
v. City of Los Angeles, supra, 153 Cal.App.3d at p. 398.) Nobody raised an
issue in Greenebaum regarding the tie vote, however, so the opinion is legally
silent on the point. Moreover,
confrontation with the certification of an EIR by a nonelected body is
consonant with the Kleist court's observation that the whole purpose of the EIR
"review and consideration function" is-to put that court's rationale
in less genteel terms-to expose the elected decision makers to the political
heat of certifying an EIR. Accordingly, another regulation, Guideline 15185,
subdivision (b), builds on the requirement of an appellate process in Guideline
15090, subdivision (b) by explicitly obligating the elected decision makers to
"consider" a certified EIR and "make findings" about it. [FN11] FN11 In Guideline 15185, subdivision (a), the syntax in the
first sentence suggests a faint whiff of a glimmer of an idea that the elected
decision makers might not be obligated to provide for appeals: "Where an
agency allows administrative appeals upon the adequacy of an environmental
document, an appeal shall be handled according to the procedures of that
agency." The "where an agency allows" language might be read to
imply that there are instances "where" an agency doesn't allow such
appeals. However, the language should not be read that way. A basic canon of
linguistic construction is that two parts of the same basic document or scheme
(such as a set of regulations) should be read as a whole to reconcile apparent
inconsistencies. (Cf. Civ. Code, 1652; see also Bingham v. CTS Corp. (1991) 231
Cal.App.3d 56, 68 [282 Cal.Rptr. 161] [reading regulations "as a
whole"].) The theory behind the rule is pretty simple: Authors, whether
they be poets, novelists, or on the staff of the office of planning and
research (see Guideline 15000) generally do not want to contradict
themselves-and when they do, their whimsy should be relatively obvious from the
text (e.g., "The sun was shining on the sea/Shining with all his might ...
And this was odd, because it was/The middle of the night"). Texts thus
generally should be read with the presumption of reconciling apparent
inconsistencies. Guideline 15090, subdivision (b) unambiguously requires an
appellate process, as does the common law construing the basic review and
consideration function in CEQA (see Kleist, supra, 56 Cal.App.3d at p. 779), so
the ambiguous "where" in Guideline 15185, subdivision (a) simply
refers to those times when a party chooses to exercise its right of appeal, not
the option given the agency to have them in the first place. The current text of
Guideline 15185, subdivision (b) is: "The decisionmaking body to which an
appeal has been made shall consider the environmental document and make
findings under Sections 15091 and 15093 if appropriate." The words
"if appropriate" certainly indicate, of course, that there may be
times when "findings" are not appropriate. There is no need in this
case, however, to limn those instances when findings might not be *528
"appropriate," because in the present case they clearly were. Appropriateness
under Guideline 15185, subdivision (b) is clearly tethered to the standards set
out in Guidelines 15091 and 15093. "Under" Guideline 15091, no public
agency may approve a project where an EIR has identified at least one significant
environmental effect "unless the public agency makes one or more written
findings for each of those significant effects, accompanied by a brief
explanation of the rationale for each finding." (Italics added.) Likewise,
Guideline 15093, subdivision (b) requires a public agency to "state in
writing the specific reasons to support its action based on the final EIR
and/or other information in the record" whenever the decision allows
"the occurrence of significant effects which are identified in the final
EIR but are not avoided or substantially lessened." At its absolute
narrowest, the "if appropriate" language in Guideline 15185,
subdivision (b) requires an affirmative "explanation" in any case
where an EIR identifies at least one significant environmental effect, which,
of course, is the case before us. The final EIR in the present case identified
a number of significant environmental impacts, including adverse air quality,
loss of 50.3 acres of coastal sage scrub, loss of 14.6 acres of Coast Live Oak
Woodland, conflict with existing wildlife movement corridors, permanent
viewshed alteration and even the night lighting glare to which we have already
referred. In sum, given an EIR here, the Orange County Board of Supervisors was
under an affirmative duty to "make findings" pursuant to Guidelines
15091 and 15093. Now we come to the
nub of the case. California Quartet and the board do not argue, on appeal, that
the board was relieved of the need to make findings in regard to Vedanta's
appeal from the planning commission's certification, but rather that it is
"ludicrous" to require the board to render findings "separate
and apart" from the commission's detailed findings. Their theory is that
by deadlocking, the default result was an adoption of the planning commission's
"detailed" findings and explanations. We do not disagree
with the idea that an elected body can adopt the findings and explanations of
the lower body. [FN12] As mentioned above, there is no reason an elected
body cannot adopt the detailed findings and explanations made by the lower
unelected body from which the Guideline 15185 *529 administrative appeal
is taken. (See Greenebaum v. City of Los Angeles, supra, 153 Cal.App.3d 391,
402-403.) FN12 There is a judicial analog here: In the past our Supreme
Court has, on occasion, simply repeated the opinion, or parts of the opinion,
of the Court of Appeal in rendering its decision. (E.g., Deas v. Knapp (1981)
29 Cal.3d 69, 74 [171 Cal.Rptr. 823, 623 P.2d 775]; Sanborn v. Chronicle Pub.
Co. (1976) 18 Cal.3d 406, 410 [134 Cal.Rptr. 402, 556 P.2d 764].) That didn't
mean, however, that the high court was any less engaged in confronting the case
(in Deas, for example, there was a separate concurring and dissenting opinion);
it simply chose not to re-do the work of the lower court. But just because the
board could have adopted findings of the planning commission here does not mean
that a tie vote has the effect of adopting findings. What the board and
California Quartet fail to appreciate is this: The very fact that "findings"
(including a Guideline 15091, subd. (a) explanation) must be made at all is
incompatible with the nature of a tie vote. A tie vote can certainly result, as
it did with Fuller's spelunkers, in an acquiescence. But it cannot constitute
an affirmative act de novo. If a board must "provide a brief
explanation" of the "rationale" of any findings regarding
"significant environmental effects" identified in the EIR (Guideline
15091, subd. (a)), or "state in writing the specific reasons to support
its action" when there are significant effects not substantially mitigated
(Guideline 15093, subd. (b)), it is by necessity forced to act in a conscious,
aware, deliberative manner. In effect, CEQA requires not only de novo review by
a board of supervisors, but de novo fact finding as well. Elected decision
makers faced with appeals under CEQA from unelected bodies thus do not have the
luxury of playing Hamlet. Findings and adoptions of findings are by nature
affirmative acts. They are, in essence, literary acts by authors, even if those
authors only recapitulate earlier work. Inherent in a consideration and finding
requirement is that the body of elected decision makers must take unambiguous
action, and unambiguous action means decision makers cannot be evenly divided against
themselves. In CEQA terms, they have no alternative to taking arms against the
troubles identified in the EIR; they do not have the option of suffering them
silently. The affirmative
nature of the confrontation with the EIR required under CEQA is illustrated by
City of Carmel-by-the-Sea v. Board of Supervisors (1977) 71 Cal.App.3d 84 [139
Cal.Rptr. 214], which dealt with whether a zoning administrator had properly
considered "all issues raised in the EIR before making his decision
regarding the issuance of use permits." (Id. at p. 95.) [FN13] The
zoning administrator ducked consideration of air pollution, and water or
traffic considerations, saying that such matters were legislative decisions for
the board of supervisors. The Court of Appeal ultimately rejected that
position, noting that the administrator's refusal to consider the *530
air, water and traffic aspects of the project meant he had "abdicated the
responsibility to make decisions on environmental matters ...." (Id. at p.
96.) The appellate court looked for evidence of some real confrontation by the
administrator with the economic and social values in the project, and, finding
none, concluded his findings were insufficient to support his decision. (Ibid.) FN13 In City of Carmel-by-the-Sea there was no issue of whether
there was any improper delegation to the zoning administrator; the plaintiffs,
in fact, appeared to have accepted the administrator's role as having "the
prime decision-making authority on environmental matters." (City of Carmel-by-the-Sea
v. Board of Supervisors, supra, 71 Cal.App.3d at p. 95.) We therefore preceive
no tension between Kleist (city council could not delegate EIR review to
special board) and City of Carmel-by-the-Sea. B. Disposition of the Board's and California Quartet's
Various Arguments 1. The County Did Not Provide (and Could Not Have Provided)
for Certification of the EIR by Tie Vote The appellants' core
argument is a gloss on Guideline 15185, subdivision (a), which provides that
"Where an agency allows administrative appeals upon the adequacy of an
environmental document, an appeal shall be handled according to the procedures
of that agency." They argue that here the board indeed adopted internal
procedures allowing for the certification of an EIR (and presumably, for the
adoption of findings by the planning commission) by a tie vote. This argument,
however, fails both generally and specifically. The general reason it fails is
that tie votes are incompatible with the kind of affirmative action implied in
Guidelines 15185, subdivision (b), 15091, subdivision (a) and 15093,
subdivision (b). As we have said, a board cannot validly provide for an
approval of an EIR by tie vote. In doing so, it would be circumventing the
protections provided by CEQA to expose elected decisionmakers to the political
consequences of any decision to certify an EIR. There is a sort of grand design
in CEQA: Projects which significantly affect the environment can go forward,
but only after the elected decision makers have their noses rubbed in those
environmental effects, and vote to go forward anyway. The argument also
fails specifically, because in point of fact the board did not adopt procedures
allowing for certification of EIR's and adoption of planning commission
findings regarding EIR's by tie vote. [FN14] First, there is nothing in
the set of special procedures adopted in November 1997 by the county in
anticipation of Vedanta's particular appeal that allows for approval by tie
vote. Those procedures, if anything, excluded the possibility of an *531
approval by tie vote because they required the board to "consider the
appeal at a public meeting and make a determination whether to uphold the
appeal in whole or in part or to deny the appeal." (Italics added.) Making
a "determination" implies affirmative action, disconsonant with
passively not disturbing the work of a subordinate body. Moreover, the adopted
procedures specifically identified three contingencies-expiration of the appeal
period without an appeal, "denial of any appeal and ratification of the
Planning Commission's certification" or "certification" of the
EIR "by the Board of Supervisors with modifications," which would
mean that the "Building Official may issue the grading permit." The negative
implication of the identification of the three contingencies (expressio unius
est exclusio alterius) is that an unidentified contingency would result in the
building official's not being able to issue any grading permit. FN14 Which actually is to be expected. The very act of explicitly
writing down such a procedure would focus the county counsel doing the drafting
on the various findings and explanation requirements set forth in the
regulations, illustrating the fundamental incompatibility of tie votes and
affirmative findings. The same applies to a
county ordinance, section 7-9-157 of the Codified Ordinances of the County of
Orange, on which the board and California Quartet heavily rely. County code
section 7-9-157 provides that if an action on a discretionary permit, zone
change, or zoning code amendment results in a tie vote by the decisionmaking
body, that tie vote "shall constitute disapproval" of the permit,
permit appeal, proposed permit revocation, proposed zone change, or proposed
zoning code amendment. [FN15] As the trial court noted, the ordinance
does not address EIR's, which, as we have shown, are tightly controlled by CEQA
and CEQA regulations in imposing affirmative requirements of written findings. FN15 Here is the exact text of County Code section 7-9-157:
"If action on a discretionary permit per section 7-9-150 or a zone change
or Zoning Code amendment per section 7-9-103, 7-9-155, or 7-9-156 results in a
tie vote by the decision-making body, that shall constitute disapproval of the
(1) proposed permit, (2) permit appeal (i.e., original action stands), (3)
proposed permit revocation [(] permit remains valid), (4) proposed zone change
(including amendments to specific plans and planned communities), or (5)
proposed Zoning Code amendment, as applicable." To the same effect
are the County of Orange Environmental Analysis Procedures, adopted in June
1985, which again, if anything, militate against approval by deadlock. Under
the heading "EIR Approval and Certification," the county's
environmental procedures state: "Where the Planning Commission is not the
decision making body, it shall render its opinion in writing (and such may be
indicated in its minutes) and such opinion shall be considered by, but not
binding upon, the decision making body." (Italics added.) The directive to
affirmatively "consider," without any indication that the lower
body's action is "binding," would in ordinary circumstances lead to
the conclusion that affirmative action on the part of the board was *532
necessary; inaction would not de facto ratify the decision of the planning
commission. Finally, there is the
"policy" or custom of the board, spelled out in a declaration of a
supervising deputy county counsel submitted in opposition to the summary
adjudication motion. That declaration avers "it is the policy of the
County that, in the case of a tie-vote on an appeal of a discretionary permit
approval or other discretionary action such as an EIR certification, that the
appeal is not upheld and the lower administrative body's decision stands."
In line with this alleged "policy," the same deputy county counsel,
prior to the public hearing portion of the February meeting that resulted in
the two-to-two tie, was asked by Supervisor Spitzer "what would happen if
there were not three votes to uphold the appeal? Then what would happen by
default?" His answer: "The decision of the Planning Commission would
remain in effect." The declaration was
irrelevant to the summary adjudication motion. [FN16] Going back to the
general point, the Guideline requirements for affirmative action necessarily
trump any local custom which would have the effect of obviating those
requirements. Additionally, the "procedures" language in Guideline
15185, subdivision (a) necessarily contemplates written procedures which can be
ascertained beforehand, not some unwritten local custom or "policy,"
which, by definition, would be at best only haphazardly discovered. FN16 The trial court struck the declaration, which the appellants claim was error. While the trial court didn't need to go so far as to strike the declaration, it was all much of a muchness in terms of its effect on the result. In the language of summary adjudication, the deputy county counsel's declaration simply failed to raise any material issue of fact, and therefore made no difference to the moving parties' entitlement to the adjudication. 2. The Exhaustion of Remedies Doctrine Is No Bar to This
Lawsuit The county did not
have any written procedures providing for approval of EIR's by tie votes of the
board, and it could not have had any and been in compliance with the CEQA
Guidelines. At most it had an unwritten custom which the board had to be
reminded of before the February vote. Given these facts, it is obvious that the
board's and California Quartet's claim that the plaintiffs did not exhaust
their administrative remedies with regard to the effect of the February vote is
meaningless. It was not Vedanta that was in need of a remedy in the wake of the
failure of certification that was the result of the two-to- two tie vote. *533 3. The Addendum Did Not Cure the Fact That the Original EIR
Was Never Validly Certified The board voted three
to one in December 1998 to adopt a resolution declaring that the 299-unit
project did not "trigger the preparation of a subsequent EIR" and
that a mere addendum would suffice for the already certified EIR. The
appellants contend that the three-to-one affirmative December vote made the
earlier February two-to-two tie moot, but the three-to- one vote could not
render Vedanta's challenge moot because the resolution offered by Supervisor
Spitzer was not a straight vote on the EIR or the project. It was a vote on
whether an "addendum" to an EIR which (as the resolution makes clear)
the board believed had already been certified, was required under CEQA, or
whether something more was necessary, such as a "subsequent" EIR. [FN17]
Specifically, the board found that "per Section 15164 of the CEQA
Guidelines, the proposed Contingency Plan meets all the criteria which would
allow the preparation of an Addendum to Certifed [sic] FSEIR 566." FN17 Indeed, a public notice regarding the proposed subdivision
of the property into 299 lots for single-family residential development put out
by the subdivision committee of the planning commission in October 1998 stated
that "the project [was] within the scope of previously finalized EIR
566." Under Guideline
15164, an addendum may be prepared to a "previously certified EIR if some
changes or additions are necessary but none of the conditions described in
Section 15162 calling for preparation of a subsequent EIR have occurred."
(Italics added.) As we have explained above, this EIR was never validly
certified. A vote to allow an addendum made on the assumption that it already
was certified cannot substitute for a vote certifying the EIR in the first
place. We need only point out in that regard that if such a procedure were
valid under CEQA, it would allow decisionmaking bodies to circumvent the
political scrutiny built into the CEQA process, because one decision maker could
use an abstention as a de facto "yes" vote, and then later hide
behind a subsequent overt "yes," vote on the theory that the second
vote only involved a technical or housekeeping matter on a project that was
already inevitable. ("Who? Me take responsibility for approving this
project?") The
failure-to-exhaust-administrative-remedies argument with regard to the addendum
leveled against Vedanta and the other plaintiffs is simply erroneous. A letter
from the plaintiffs' attorney sent to the Orange County Planning and
Development Services Department dated August 25, 1998, *534 gave fair
notice of the problem of the adequacy of the certification of the EIR, [FN18]
even assuming the lawsuit filed the previous March was not sufficient. [FN19] FN18 A list of 16 objections to the addendum was attached to the
letter, No. 14 of which was that the county had "violated CEQA and the
CEQA Guidelines in that it has improperly relied upon FSEIR 566, which is a
legally inadequate CEQA document that was improperly certified for the reasons
set forth in that certain 'Complaint for Declaratory Relief and Petition for
Writ of Mandate,' which is attached hereto as Exhibit 'C' and is incorporated
herein by reference ...." FN19 We are therefore spared the need for a disquisition on the
futility exception to the exhaustion doctrine. 4. Declaratory Relief Was Available California Quartet
asserts that the trial court could not have granted Vedanta declaratory relief
because administrative mandamus (see Code Civ. Proc., 1094.5) was its exclusive
remedy. Not so. There is nothing incompatible between administrative mandamus
and declaratory relief. (E.g., J. L. Thomas, Inc. v. County of Los Angeles
(1991) 232 Cal.App.3d 916, 924 [283 Cal.Rptr. 815] [person has standing to
challenge facial validity of statute in declaratory relief without exhausting
administrative remedies]; Subriar v. City of Bakersfield (1976) 59 Cal.App.3d
175, 195 [130 Cal.Rptr. 853] [constitutional questions could be reached by
action for declaratory relief independent of administrative mandamus].) More to
the point, though, Vedanta's declaratory relief claims did not challenge any
specific adjudicatory or "quasi-judicial" act of the board. It simply
sought resolution of the controversy over the legal effect of the tie vote.
Declaratory relief has been used without comment to ascertain the effect of tie
votes in non-CEQA contexts (Dry Creek Valley Assn., Inc. v. Board of
Supervisors (1977) 67 Cal.App.3d 839 [135 Cal.Rptr. 726]), and declaratory
relief is tailor-made for a case such as this one, centered as it is on a pure
question of law-whether the board even made a decision-not a question of
whether an administrative record contained substantial evidence to support a
decision that the agency unquestionably did make. IV. Conclusion In affirming the
judgment, we rule on a narrower basis than the trial court, which held that the
tie vote was not an "act" within the meaning of Government Code
section 25005 ("No act of the Board shall be valid or binding unless a
majority of all the members concur therein."). That is, we do not reach
the question as to whether a tie vote by an elected local body (such as a city
council or a county board of supervisors) in non-CEQA cases *535 might
have the effect of affirming the decision of a non-elected local body, such as
a planning commission. CEQA and its regulations are sufficient to uphold the
trial court's decision here. We also emphasize the
narrowness of our decision in terms of the issues that we do not address. Our
decision only goes to whether the board validly certified the EIR, not what the
consequence of the failure to do so is. The parties have not argued the
question of where the case goes from here, and, in particular, what happens
when a lead agency fails to certify an EIR within applicable time frames, which
at the outside are not to exceed one year. (See Pub. Resources Code, 21151.5,
subd. (a)(1)(A).) We simply note that a developer is not without a remedy for a
lead agency's failure to certify an EIR because it deadlocked on the vote. The
recent case of Sunset Drive Corp. v. City of Redlands (1999) 73 Cal.App.4th 215
[86 Cal.Rptr.2d 209] makes it clear that a petition for writ of mandate and a
complaint for damages under 42 United States Code section 1983 are available
for an agency's refusal to act in failing to complete and certify an EIR. (See
Sunset, supra, 73 Cal.App.4th at pp. 221 [mandamus available for refusal of
city to complete EIR] and 225 [damages for violation of federal civil rights
available because agency may not arbitrarily refuse to complete an
"adequate" EIR].) The political heat
rationale thus cuts both ways: A vote to refuse to certify an EIR, or an
absention (which, as we have seen, is the same) is not exactly a
"cheap" no vote. A detailed exploration of the board's inaction,
however, can await another day. Respondents shall recover their costs on
appeal. Rylaarsdam, J., and
Bedsworth, J., concurred. *536 Cal.App.4.Dist.,2000. VEDANTA SOCIETY OF
SOUTHERN CALIFORNIA, Plaintiff and Respondent, v. CALIFORNIA QUARTET, LTD., et
al., Defendants and Appellants. NORBERTINE FATHERS OF ORANGE et al., Plaintiffs
and Respondents, v. CALIFORNIA QUARTET, LTD., et al., Defendants and
Appellants. ENDANGERED HABITATS LEAGUE, INC., et al., Plaintiffs and Respondents,
v. CALIFORNIA QUARTET, LTD., et al., Defendants and Appellants. END OF DOCUMENT CERTIFIED FOR PUBLICATION Document URL: http://ceres.ca.gov/ceqa/cases/2000/Vedanta-2000.html Copyright © 1998-2003 California Resources Agency. All rights reserved. |